SCANA to stop building new nuclear units at V.C. Summer

South Carolina Electric & Gas Co. (SCE&G), unit of SCANA Corp. will cease construction of the two new nuclear units at the V.C. Summer Nuclear Station in Jenkinsville, SC and will promptly file a petition with the Public Service Commission of South Carolina seeking approval of its abandonment plan.

This decision was reached by SCE&G after considering the additional costs to complete the Units, the uncertainty regarding the availability of production tax credits for the project, the amount of anticipated guaranty settlement payments from Toshiba Corp., and other matters associated with continuing construction, including the decision of the co-owner of the project, the South Carolina Public Service Authority (Santee Cooper), the state owned electric utility, to suspend construction of the project.

Based on these factors, SCE&G concluded that it would not be in the best interest of its customers and other stakeholders to continue construction of the project.

Following the bankruptcy filing of Westinghouse Electric Co. (WEC), SCE&G and Santee Cooper each began a comprehensive process of evaluating the most prudent path forward for the Units. The project owners worked with WEC and Fluor Corp., as well as other technical and industry experts, to evaluate the project costs and schedules.

Based on this evaluation and analysis, SCE&G concluded that completion of both Units would be prohibitively expensive. According to SCE&G’s analysis, the additional cost to complete both Units beyond the amounts payable in connection with the engineering, procurement, and construction contract would materially exceed prior WEC estimates, as well as the anticipated guaranty settlement payments from Toshiba.

Moreover, the units would need to be online before January 1, 2021, to qualify for production tax credits, under current tax rules. SCE&G’s analysis concluded the Units could not be brought online until after this date.

SCE&G also considered the feasibility of completing the construction of Unit 2 and abandoning Unit 3 under the existing ownership structure and using natural gas generation to fulfill any remaining generation needs.

This option provided a potentially achievable path forward that may have delivered SCE&G a similar megawatt capacity as its 55 percent interest in the two Units and provided a long-term hedge against carbon legislation/regulation and against gas price volatility. SCE&G had not reached a final decision regarding this alternative when Santee Cooper determined that it would be unwilling to proceed with continued construction of two Units or one Unit. Consequently, SCE&G determined that it is not in the best interest of customers and other stakeholders for it to continue construction of one Unit.

Based on this evaluation and analysis, and Santee Cooper’s decision, SCE&G has concluded that the only remaining prudent course of action will be to abandon the construction of both Unit 2 and Unit 3 under the terms of the Base Load Review Act (BLRA).

a man standing next to a monitor

Sense smart meter software gives utilities a real-time look at the grid edge

Sense software embedded in smart meters can help utilities get a better look at the grid edge, as CEO Mike Phillips explains at DTECH.
a G&W Electric Viper-ST recloser

G&W Electric shows off next-gen recloser amongst transmission and distribution solutions at DTECH

G&W Electric is presenting a variety of transmission and distribution solutions at DTECH, including its next-generation Viper-ST recloser.