September 11, 2003 [SolarAccess.com]Sweden-based Benima has been commissioned by Aker Kvaerner to supply the control system, including its programming, for the energy from waste boiler plant being supplied to power utility Boras Energi. Modern recycling methods and new regulations prohibiting the dumping of combustible refuse have led Boras Energi to invest in two new energy from waste boilers that will be integrated with an existing district heating power plant. The two new 20 MW boilers will be fuelled by sorted combustible household and industrial waste, recovered wood chips and biofuels and used both to supply district heating and to produce electricity. Aker Kvaerner’s subsidiary, Kvaerner Power, in Gothenburg, has commissioned Benima to supply the control system and its programming.