India May Defer Penalties on $1 Billion of Solar Thermal Plants

India May Defer Penalties on $1 Billion of Solar Thermal Plants

India's Ministry of New and Renewable Energy is seeking to defer penalties on about $1 billion of solar-thermal power projects that are delayed by a lack of water, financing difficulties and equipment shortages.

Seven projects totaling 470 megawatts in capacity by companies including by Godawari Power and Ispat Ltd., Reliance Power Ltd. and Lanco Infratech Ltd. that were to be ready by May, aren’t operational, Tarun Kapoor, joint secretary at the ministry, said in a phone interview from New Delhi. The projects could potentially forfeit about 2.3 billion rupees ($42.5 million) in performance guarantees, according to rules when the contracts were awarded in December 2010.

“There’s obviously a problem since all are delayed,” Kapoor said. “This is the first time solar-thermal projects are being built in India and we want them to succeed.” An expert committee at the ministry is recommending a 10-month extension for the projects, he said.

The delays are another blow to the solar-thermal industry suffering from high costs. France’s Areva SA had to scrap plans for a A$1 billion complex in Australia in November after failing to get financing. In contrast, a competing technology, solar photovoltaic, has benefited from a 61 percent plunge in panel costs over the past two years, according to data compiled by Bloomberg.

Solar-thermal plants, which focus sunlight on liquids to produce steam and drive turbines, are valued for their ability to store energy and produce power around the clock. Photovoltaic panels convert sunlight directly into electricity and need batteries for storage.

Godawari Ahead

A 50-megawatt project owned by Godawari Power is the closest to completion, Kapoor said. It’s undergoing final testing and should be finished by early June. Godawari Power’s Managing Director B.L. Agrawal wasn’t immediately available for comment.

A 100-megawatt project owned by billionaire Anil Ambani’s Reliance Power is about six months behind schedule, Kapoor said. A delay in laying a water pipeline by Rajasthan state authorities to the site stalled the plant, according to a letter sent by the Rajasthan government toRenewable Energy Minister Farooq Abdullah in March. Reliance Power spokesman Nagraj Rao declined to comment.

Lanco Infratech spokeswoman Deepkamal Kaur didn’t respond to an e-mail seeking confirmation of delays at its 100-megawatt plant. The company is also the contractor for KVK Energy & Infrastructure Pvt.’s 100-megawatt solar-thermal project.

The Indian projects, ranging from 20 megawatts to 100 megawatts in capacity, are using turbines from suppliers including Siemens AG, General Electric Co. and Areva.

India has built 1,686 megawatts of solar capacity and expects to award an additional 500 megawatts of solar-thermal capacity by 2017, Kapoor said. The outcome of the plants under construction could affect those plans, he said.

“It depends on how the technology behaves,” he said.

Copyright 2013 Bloomberg

Lead image: Delayed sign via Shutterstock

RELATED ARTICLES

The Big Question: What Is the Most Frustrating Part about Working in Renewable Energy?

Renewable Energy World Editors

Every industry has its challenges and misunderstandings. Sometimes the obstacles we face in simply trying to do our jobs can be very frustrating.

ViZn Flow Batteries

ViZn Turns to Jabil to Meet Growing Demand for Flow Batteries

Andrew Burger, Correspondent Energy storage startup ViZn, developer of advanced zinc-iron flow battery technology, is scaling up the size and scope of its operations as it works to meet growing demand from a variety of customers both in the U.S. and a...
Norway and Sweden flags

Nordic Renewables Boom Set to Exceed Wind Energy Target

Jesper Starn, Bloomberg

Sweden and Norway will probably exceed a joint target for renewable energy production by the end of the decade, industry consultant Nena AS said.

Renewable energy community

State and Metro Governments, Consumer Actions Drive Dramatic Shift in US Energy Landscape

Ron Pernick, Clean Edge The United States is experiencing a significant shift in its energy landscape. Last year, utility-scale wind and solar power combined for 47 percent of new generation capacity in the U.S. Based on this expansion, 11 states...

CURRENT MAGAZINE ISSUE

Volume 18, Issue 3
1505REW_C11

STAY CONNECTED

To register for our free
e-Newsletters, subscribe today:

FEATURED PARTNERS



EVENTS

PV-301: Advanced PV Design & Installation

This highly desirable and advanced course is intended for the profession...

PV-401: Advanced Field Training

Real world on the job solar installation, training, and experience is th...

PV-201: Introduction to PV Design & Installation

PV 201 Introduction to PV Design & Installation is simply the best i...

COMPANY BLOGS

Solar Tracking – A Key Technology for Unlocking the Full Potential ...

Quotes for very large solar photovoltaic projects in sunny parts of the ...

What is Distributed Energy and Why Does It Matter to Solar?

Distributed energy has become a hot topic of conversation in energy circ...

Meteorological Technology International Magazine - SENSORS AND SENS...

Over the past 10 years, these sensing technologies have spread tre...

SOCIAL ACTIVITY

Tweet the Editors! @megcichon @jennrunyon

NEWSLETTERS

Renewable Energy: Subscribe Now

Solar Energy: Subscribe Now

Wind Energy: Subscribe Now

Geothermal Energy: Subscribe Now

Bioenergy: Subscribe Now  

 

FEATURED PARTNERS