Avoiding Explosive Consequences: Five Lessons from the Offshore Wind Sector

The emergence of a U.S. offshore wind sector presents a great opportunity for would-be project developers looking to exploit 4,000 GW of generation potential off the East and West coasts and in the Gulf of Mexico. If and when the sector can overcome regulatory, financial and political hurdles, early project lease winners on the East Coast will soon be joined by countless others in building North America’s first offshore wind farms.

As these developers seek permission and edge towards financial close, they will start to think about some of the technical challenges that they will face during the early development phases of these projects. In doing so they will no doubt look to the experience of their counterparts in the European sector for insight into some of the specific risks involved in the construction of marine energy infrastructure. 

One such risk is the unique threat posed by unexploded ordnance (UXO). Well-publicised in European waters — where a legacy of thousands of tons of sea mines and bombs left behind by two World Wars is a recognised obstacle to safe and timely project delivery — the risk is also prevalent in U.S. waters. 

Off the East Coast and in the Gulf of Mexico in particular, preliminary desk studies and threat mapping based on publically available resources, such as National Oceanic and Atmospheric Administration (NOAA) charts and Department of Defense records have identified UXO risk “hot spots.” These include munitions dump locations and sites of historic or modern military training. 

While the scale of the threat has not yet been fully quantified, at least 100,000 tons of expired chemical weapons are known to have been dumped in U.S. waters between 1945 and 1968 — and this dumping continued well into the 1970s. Combined with significant abandonment of conventional munitions and military training and testing, this has generated a background threat to the majority of the East Coast and the Gulf of Mexico, as well as a similarly documented threat off the West Coast.

Any intrusive activity on the seabed — whether it be drilling, cable laying, or driving of monopile foundations for wind turbines — is capable of causing the unintended detonation of UXO in the vicinity and not only jeopardizing the safety of workers on site but also damaging vessels and installation infrastructure. The European experience is that the detonation of UXO can cause significant project delay, which has cost millions of dollars.

Gulf of Mexico, South and North Atlantic Unexploded Ordinance (UXO) Threats

This proven UXO presence in North American waters will therefore require offshore wind developers to take appropriate and timely action to mitigate the inherent financial, safety, schedule and construction risks.

In doing so, I would urge them to learn from their European counterparts by taking heed of the following lessons: 

1) UXO may be on site and will cause problems if mismanaged.

Many of the issues caused by unexploded ordnance in the European marine energy sector to date have resulted from inherent misunderstandings on behalf of the developer or grid operator regarding the scale and nature of the UXO threat to their project sites, and who is ultimately responsible for managing this risk.

While inadvertent detonation of UXO on a marine construction site is an extremely rare occurrence, the discovery of munitions can compromise a project. A number of instances in the European sector have shown that often the most tangible risk posed by the unexpected discovery of UXO is the potential for significant project delay and contractual dispute, which, in turn, brings about substantial, unforeseen financial consequences.

The identification, by geophysical survey, of anomalies that model as UXO in the vicinity of planned project infrastructure will necessitate the establishment of an exclusion zone whilst investigative and/or disposal procedures are carried out. As many as 60 vessels may be chartered on site at any one time during construction and, for the duration of this work, they may be sidelined. The cost of hiring a single jack-up barge can be as much as $350,000 per day, so any project delay is clearly capable of quickly eroding contingency sums. 

In addition to the risk of costly project delay, failing to demonstrate that appropriate measures have been taken to mitigate the explosive threat to technicians and vessel operators on site puts developers at risk not only of jeopardizing worker safety but also of contractual dispute that can further compound these problems. 

A case in point is the Riffgat Offshore Wind Farm in the German North Sea, which experienced lengthy setbacks as a result of a dispute between grid operator TenneT and the project developer regarding the responsibility and the risk management protocols for dealing with UXO along the export cable routes. The failure of initial studies to accurately identify the prospective quantity of UXO or its locations on the seabed resulted in an estimated €100 million of unforeseen costs — €37 million of which was spent on munitions clearance and €53 million on compensation for project delays.

2) Early identification of the local UXO threat is critical.

Scenarios as outlined above can be avoided through proactive, timely management during the early project-planning phases.

Given the increased level of technical complexity and the project delays associated with the safe removal of threats from the vicinity of an existing turbine foundation or subsea cable, we estimate that it is at least ten times more expensive to reduce UXO risk once a project is underway, compared with managing the risk proactively before geotechnical investigation and installation commences. 

As such, the earlier a developer starts considering the threat of UXO on site, the better. Preliminary UXO threat studies making use of local records and historical information are an important starting point and can provide a quick overview of potential threats before a detailed threat and risk assessment using high-resolution detailed records and charts is undertaken. 

#rewpage#

3) The design and communication of UXO risk mitigation measures is vital. 

The data obtained from these early-stage UXO surveys should inform the design of a comprehensive risk management strategy tailored to the investigative or construction procedures due to take place on site. 

Once this strategy has been outlined, the design and specification of risk mitigation measures can follow. It’s highly important that the parameters of geophysical survey for UXO in the threat spectrum are clearly outlined to the specialist contractors due to undertake the work.

The employment of vessel-mounted gradiometry and side-scan sonar techniques is only worthwhile if it is proven to detect the smallest anomalies that pose a UXO threat. Geophysical survey for UXO need not identify the smallest threat, only the smallest that might present a risk, which cannot be tolerated.

4) UXO can be safely avoided, rather than cleared expensively.

One of the key advantages of a comprehensive, accurate site survey, specified and analyzed by trained munitions experts is that it not only pinpoints threats that will directly influence planned turbine sites and cabling routes and will therefore need to be safely removed, but also allows developers to avoid UXO. Depending on the flexibility of the plans in place, it can afford them the opportunity to mitigate UXO risk by means of small adjustments to project design that ensure critical project infrastructure remains at a safe distance from known threats, thus preventing its prospective initiation.

In this way the financial impact of UXO management can be reduced. Many Explosive Ordnance Disposal (EOD) contractors would advocate a 100 percent clearance approach that is both expensive and unnecessary. Developers’ legal responsibilities, in the UK and EU, are to reduce project risks to a level that is As Low As Reasonably Practicable (ALARP). This can be safely and efficiently achieved without investigating and removing every single object resembling a bomb, torpedo or mine on site. Similarly, because even the best/highest resolution geophysical surveys for UXO are likely to generate a high number of “false positive” targets (i.e. scrap metal that resembles UXO), its investigation and removal is often prohibitively expensive. 

5) Better informed UXO planning de-risks a project and drives cost efficiency. 

For a developer, knowing a) exactly what their legal responsibility is regarding safe management of UXO and b) what their risk management and mitigation options are is a crucial step towards keeping a lid on the costs of dealing with the threat appropriately and efficiently.

Seeking the advice of an experienced UXO risk management consultancy from an early stage, or, at the very least, accounting for the threat with the internal appointment of a qualified UXO risk manager should ensure that any UXO presence on site is dealt with safely and in a cost effective manner. 

By following the example of a whole host of European offshore wind project developers that have acted proactively and appropriately to manage the UXO threat, the pioneers of the U.S. offshore wind industry can avoid the problems encountered by those who have mismanaged it and realize that the price of ameliorating this explosive risk need not run into the millions.

Untitled Document

Get All the Renewable Energy World News Delivered to Your Inbox

Subscribe to Renewable Energy World or email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

RELATED ARTICLES

offshore wind

Hitachi Plans to Add Production Line for Offshore Wind Parts

Chisaki Watanabe, Bloomberg Hitachi Ltd. plans to expand its reach into the market for offshore wind projects by adding a production line to make...
Renewable energy

Leading US ICT Companies Renewables Use at 14%, and Growing

Andrew Burger Electricity consumption in the global information and communications technology (ICT) industry is growing rapidly. An...
Wind farms

Western: Streamlined Environmental Review Process for Wind Farms in Midwest ‘Takes Effect Right Away’

Jennifer Delony Western in an Aug. 26 record of decision (ROD) adopted a standardized process for collecting information and evaluati...

NextEra Commits to Hawaii’s Clean Power Goal, Local Management

Lynn Doan, Bloomberg NextEra Energy Inc. and Hawaiian Electric Industries Inc. made 50 new commitments as part of their proposal to merge ...

PRESS RELEASES

Canadian Solar Wins Five Solar Power Projects Totaling 185 MW in Brazil

These power projects were won under a 20-year Power Purchase Agreement (PPA) with the B...

$100 Off of 5-day Advanced PV Project Experience. Download a Topic Schedule.

Assemble, ground, energize, and commission a complete grid-tied SolarEdge system from s...

Former Australian Prime Minister Kevin Rudd talks politics of fear vs. politics of hope

Rudd, who led the Australian parliament from 2007 to 2010, told the Summit audience tha...

Intersolar AWARD „Solar Projects in India“ – Applications being accepted until September 18

The Intersolar AWARD in the category Solar Projects in India honors projects in the fie...

FEATURED BLOGS

Washington, DC Bridges the Solar Gap

The District of Columbia has enjoyed 15 years of strong economic growth. But prosperity is spread unevenly across the...

Sell Through Hypothesis

You first learned to hypothesize, or make educated guesses, in grade school science class. Now it’s time to ref...

Cronimet / THEnergy study: In solar for mines size does not always matter - Reducing CAPEX with energy efficiency and load shifting

Munich, September 2015. Mining companies are constantly gaining interest in solar solutions because frequently solar ...

Final Program Now Available for GRC Annual Meeting & GEA Geothermal Energy Expo

GRC Annual Meeting & GEA Geothermal Energy Expo - Final Program from

FINANCIAL NEWS

Simon Cooke is managing director of 6 Alpha Associates, a specialist risk consultancy practice, with particular expertise in the assessment and management of unexploded ordnance (UXO) risk. Having served as a Major in the Corps of Royal Engineers,...

CURRENT MAGAZINE ISSUE

Volume 18, Issue 4
1507REW_C11

STAY CONNECTED

To register for our free
e-Newsletters, subscribe today:

SOCIAL ACTIVITY

Tweet the Editors! @jennrunyon

FEATURED PARTNERS



EVENTS

Doing Business in Europe – in partnership with GWEC, the Global Win...

There is now 128.8 GW of installed wind energy capacity in the EU (appro...

Doing Business in South Africa – in partnership with GWEC, the Glob...

Wind Energy in South Africa has been expanding dramatically, growing fro...

Distributed Wind Energy Workshop

Description: Distributed wind energy is electricity that is produced for...

COMPANY BLOGS

Clean Energy Patents Maintain High Levels in First Quarter, Solar L...

U.S. patents for Clean Energy technologies from the first quarter of 201...

Koch Professor drops his Koch title, still makes same errors plus s...

The Koch Professor’s title isn’t the only thing that’s...

Fact Check: AWEA represents American wind power

The American Wind Energy Association (AWEA) is proud of its members for ...

NEWSLETTERS

Renewable Energy: Subscribe Now

Solar Energy: Subscribe Now

Wind Energy: Subscribe Now

Geothermal Energy: Subscribe Now

Bioenergy: Subscribe Now  

 

FEATURED PARTNERS