Dominion Complains about North Carolina Solar Projects

The North Carolina Utilities Commission on July 3 ordered a solar power developer to respond to a Dominion North Carolina Power complaint that it may have broken a 15-MW power project into three 5-MW segments to slip it in under a 5-MW per project limit.

  • On May 12, Tyner Gliden Solar LLC filed an application for a certificate of public convenience and necessity (CPCN) for construction of a 5-MW solar photovoltaic facility to be located on Gliden Road in Tyner, Chowan County, N.C.
  • On May 12, Chowan Gliden Road Solar LLC applied for a CPCN for construction of a 5-MW solar photovoltaic facility to be located on Gliden Road in Tyner in Chowan County.
  • And also on May 12, Gliden Jehu Solar LLC sought a CPCN for construction of a 5-MW solar photovoltaic facility to be located on Gliden Road in Tyner in Chowan County.

On June 26, Virginia Electric and Power d/b/a Dominion North Carolina Power filed a petition to intervene and complaint in these three dockets. DNCP noted that these three applications said that the companies intend to sell electricity to DNCP under a power purchase agreement (PPA).

“DNCP opines that the Gliden LLCs intend to seek a separate PPA under DNCP's Schedule 19-FP, Power Purchases from Cogeneration and Small Power Production Qualifying Facilities, for each of the three Gliden LLCs' facilities,” the commission wrote in the July 3 order. “DNCP notes that Schedule 19-FP is available only to qualifying facilities (QFs) having a capacity of 5 MW or less. DNCP sets forth a number of factors that it submits show that the facilities being built by the Gliden LLCs are virtually identical.

"Further, DNCP discusses several legal and policy reasons that DNCP maintains are the basis on which the Commission should refuse to treat the Gliden LLCs' as three separate 5-MW facilities," the order said. "In particular, DNCP asserts that allowing the Gliden LLCs to receive avoided cost rates under DNCP's Schedule 19-FP would be harmful to DNCP's ratepayers because such rates would not accurately reflect the avoided costs achieved by the Gliden LLCs' facilities and would shift risks to DNCP's ratepayers. Therefore, DNCP concludes that the facilities being proposed by the Gliden LLCs should be considered to be one 15-MW facility for the purpose of determining the Gliden LLCs' eligibility for a PPA under DNCP's Schedule 19-FP.”

DNCP requests that the commission rule that the proposed facilities of the Gliden LLCs constitute one 15-MW facility for purposes of determining each Gliden LLC’s eligibility for a PPA under Schedule 19-FP. The commission gave these companies a July 28 deadline to respond to the utility’s complaints.

Said the Dominion complaint about project siting: “The CPCN applications of Tyner Gliden, Chowan Gliden and Gliden Jehu each identify Eugene N. Jordan, Inc. (‘Jordan, Inc.’) as the owner of the site that will be leased to the project company. Based on information contained on the Chowan County GIS, it appears that all three facilities will be located on a single parcel of property (Parcel No. 790300960213) owned by Jordan Inc. (the ‘Jordan Parcel’).”

Dominion added: “The Company acknowledges that if the projects are QFs, the Company is obligated to enter into an avoided cost contract with each Gliden LLC. The Gliden LLCs are not, however, eligible for a Schedule 19 contract for the reasons set forth in this Petition and Complaint. The Company does not seek a Commission ruling that each facility must be owned by a single entity. The Company recognizes that maintenance of separate corporate entities may facilitate the Gliden LLCs' future ability to sell less than all of the Gliden LLC facility to third parties.”

This article was originally published on GenerationHub and was republished with permission.

Lead image: Solar panels via Shutterstock

Untitled Document

Get All the Renewable Energy World News Delivered to Your Inbox - FREE!

Subscribe to Renewable Energy World Magazine and our award-winning e-Newsletter to stay up to date on current news and industry trends.

 Subscribe Now


US Senate Democrats Unveil Energy Bill That Restores PTC and Extends ITC

Brian Eckhouse, Bloomberg Senate Democrats unveiled a bill that would provide more tax credits for renewable energy while killing some tax ince...

US, China Solar PV Players Team Up, Invest $100MM in Chile, Uruguay and Japan

Andrew Burger Private equity infrastructure specialist Hudson Clean Energy Partners and Hong Kong-based independent power producer ...

CEO Gilles: Challenge in Geothermal is to 'Level Playing Field' with Wind, Solar

Jennifer Delony The current challenge for the geothermal energy industry is what U.S. Geothermal CEO Dennis Gilles calls “leveling th...

NRG Energy to Form Renewable Unit, Sell Wind Assets to Yieldco

Mark Chediak and Matthew Monks, Bloomberg NRG Energy Inc., the worst-performing member of the S&P 500 Utilities Index this year, said it will form a renewa...


Array Technologies Finalizes Shipments to E.ON’s Maricopa West Solar Project

Array Technologies, Inc. (ATI) has completed DuraTrack® HZ shipments to the 20 MW (ac) ...

B.C. Energy Minister to provide keynote at renewables for mines summit.

BC Minister of Energy and Mines to address the challenges of providing alternative powe...

Mining leaders seek renewables solutions at Toronto Summit

The global mining sector is facing a tough business environment with low commodity pric...

American Renewable Energy Institute Gears Up for 12th Annual Summit

"Racing Climate Change: Green Bridge with China, The Road to Paris” is the theme of th...


New Mexico Attracts Jobs and Revenues with Renewable Energy Tax Credit

New Mexico has abundant fossil fuel resources: in 2013, it ranked sixth in the nation for crude oil production, seven...

The Vice President Stole My Show (Not Really)

When I finished my Solar Power International (SPI) panel discussing what future opportunities the panelists saw in so...

The Value Of The Building

If you’re selling efficiency solutions in the built environment, you may find yourself being asked by your pros...

Sewage provides energy through processing

Many nations are investing in new technology to turn sewage waste into usable energy. Japan has recently revised its ...


Barry Cassell is Chief Analyst for GenerationHub covering coal and emission controls issues, projects and policy. He has covered the coal and power generation industry for more than 24 years, beginning in November 2011 at GenerationHub and prior t...


Volume 18, Issue 4


To register for our free
e-Newsletters, subscribe today:


Tweet the Editors! @jennrunyon



Successfully Integrating Solar: A Proactive Approach

•      What does the increasing solar penetrati...

Canadian Solar Inverters Webinar

Canadian Solar is proud to be hosting two free webinars in October! The ...

JuiceBox Energy Certified Installer Class

JuiceBox Energy is rapidly building out its national certified installer...


How To Speak, How To Listen

As sales professionals, effective communication is paramount to our succ...

Get In The Habit

We all develop habits throughout our lives. Sometimes they’re bene...

Becoming An Efficiency Sales Professional

In order to become a sales professional, you must first realize that: E...


Renewable Energy: Subscribe Now

Solar Energy: Subscribe Now

Wind Energy: Subscribe Now

Geothermal Energy: Subscribe Now

Bioenergy: Subscribe Now