Solar 1603 Grant Data Lifts the Veil On PV System Performance

In the world of photovoltaic (PV) finance, historical performance data — or the lack thereof — stands as an obstacle to the risk assessment and credit evaluation of solar installations. Investors eyeing solar-backed securities or other investment vehicles might view the asset class cautiously without a firm, data-driven understanding of how solar assets perform (i.e., generate power) in the field and how this affects the cash flows that would ultimately backstop their investment.

However, the National Renewable Energy Laboratory (NREL) has a trove of data which suggest that PV systems are, in the aggregate, performing better than expected in the field. These data are from systems installed using "grant" money from the 1603 Section of the American Recovery and Reinvestment Act which allowed for the conversion of investment tax credits into cash rebates. The data describe nearly 50,000 PV systems from 0.5 kW to 25 MW in size (with a median of 6 kW), representing a total of approximately 1.7 GW of installed capacity (see Figure 1 for the geographic distribution of these installations). Data points for each system include predicted yearly production values, actual yearly production values, zip code location, and comments regarding performance issues for each year of production.

Figure 1. Geographic distribution of analyzed installations

How much better are these systems performing in the field than they were predicted to by independent engineers and developers? As shown in Table 1, they are producing on average 2 percent to 5 percent more energy than their targets. 

Table 1. Median Ratio of Measured Over Predicted Values for All Data

Figure 2 displays the proportion of normal systems to systems that experienced identifiable issues. NREL has classified these issues into four types:

  • Project: Includes systems that incurred site-related issues, such as permitting delays, incidents where the PV system had to be removed because the roof was damaged (but not the PV installation), or the sale of a property
  • Hardware: Denotes systems with equipment problems, such as inverter outages.
  • Weather: Indicates problems associated with storm-related shutdowns, snow remaining on the systems, etc.
  • Data Collection: Comprises systems that had issues with the transmission of data and thus do not reflect the actual performance of the installed system.

As shown in Figure 2, these issues affected less than 10 percent of projects in any given year, and became less prevalent as projects got older. Typically, the incidence of problems — e.g. project delays, out-of-the-box hardware flaws, and others — is highest in the initial months of operation. Actual performance-related issues — those that arose from system functioning and not as a result of initial failures — total only 1 percent–3 percent of all systems for each year.

Note: the data points for this analysis decrease with each year, which reflects the newness of many of the 1603 systems. Only about 480, or less than 1 percent of the 48,259 systems in the dataset, have been operational for over four years.

Figure 3 shows measured production data versus predicted production data for normal systems (black-filled circles) and for systems with issues (colored symbols). Because data collection issues do not necessarily reflect the performance of the PV system and can have a broad impact range depending on how soon the issue is resolved, they have been excluded. A unity line for the normal-system data is shown as a guide to the eye.

Figure 3. Measured production versus predicted production for normal systems (red-filled circles) and for systems with issues (colored symbols). The "Data Collection" category has been excluded from this figure.

Project-related data points tend to lie farther away from the unity line. Therefore, although project- or site-specific issues may not occur as frequently as other categories, when they do occur they tend to have a larger impact on production than, for example, weather-related underperformance. In the first year, two-thirds of the project category anomalies are due to delays in permitting and constructions where cash flow has not yet commenced. In subsequent years, delays decrease to inconsequential levels, and the project category becomes dominated by operational issues.

In conclusion, the data indicate that the large majority of systems operate under "normal" conditions, and to date these systems overproduce relative to the predicted value. And, at 1.7 GW of capacity — which is 13 percent of the roughly 13 GW of total PV U.S. capacity at the end of 2013 — these 1603 projects can reasonably be viewed as a representative cross-section of the U.S. PV market.

This article was originally published on NREL Renewable Energy Finance and was republished with permission.

Lead image: Report card via Shutterstock

RELATED ARTICLES

Intersolar Europe 2015: Spirits Up, Stats Down

William P. Hirshman, Contributor Intersolar Europe, billed at the world’s leading exhibition for the solar industry, is indeed big. But Intersolar Europe 2015, one of five Intersolar-branded gatherings around the globe each year, was not as large as the an...
US Capitol

Republicans and Democrats Back Bill to Level the Playing Field for Renewable Energy

Vince Font, Contributing Editor U.S. Senators Chris Coons and Jerry Moran are leading a bipartisan effort to reintroduce tax code legislation aimed at leveling the playing field for renewable energy investment. The Master Limited Partnerships Parity Act w...
Solar thermal desalination

Solar Thermal Desalination Now Underway in Water-hungry California

Susan Kraemer, Correspondent Regional droughts are being exacerbated by climate change, which is mostly caused by what is tasked with bailing them out — fossil fuels. Israel, Australia, and now southern California have all turned to expensive energy-gu...
Memo pad on table

IRS Issues Solar Tax Equity Memo Stating the Obvious

David Burton and Richard Page, Akin Gump On Friday, the IRS issued a heavily redacted Chief Counsel Advice (“CCA”) memorandum, that addresses the intersection of solar investment tax credit partnership flip transactions and the wind production tax credit part...
Dirk Jordan is a Senior Reliability Engineer at the National Renewable Energy Laboratory. His expertise encompasses outdoor performance and degradation of individual Photovoltaic modules and entire systems.

CURRENT MAGAZINE ISSUE

Volume 18, Issue 3
1505REW_C11

STAY CONNECTED

To register for our free
e-Newsletters, subscribe today:

SOCIAL ACTIVITY

Tweet the Editors! @megcichon @jennrunyon

FEATURED PARTNERS



EVENTS

SAP for Utilities

The SAP for Utilities conference is the most comprehensive SAP for Utili...

Training: Preparing for Rule 21 - SPI 2015

What: Rule 21 Training When: September 16th @ 4:30-5:30pm Wher...

Training: NEC 2014, AFDI, & Rapid Shutdown - SPI 2015

What: NEC 2014, AFDI, & Rapid Shutdown When: September 15t...

COMPANY BLOGS

More Middle-Class Massachusetts Residents Are Going Solar

Massachusetts is known for the Pilgrims, Boston cream pie and its excell...

Harnessing Emotions

Think about how you interact with your prospects. Are you going from the...

What Solar Markets Around the World Look Like in 2015

Solar power has gained international attention as one of the best clean-...

NEWSLETTERS

Renewable Energy: Subscribe Now

Solar Energy: Subscribe Now

Wind Energy: Subscribe Now

Geothermal Energy: Subscribe Now

Bioenergy: Subscribe Now  

 

FEATURED PARTNERS