Navigating the Winding Road of Geothermal Project Financing, Part I

It is no secret that renewable energy project development cycles present many unique challenges — as well as promising opportunities — for developers, investors and power users alike. Geothermal energy project development in particular can be a challenging endeavor, based on the extended timelines involved in successfully proving a resource, mitigating drilling risk and managing the subsurface reservoir on an ongoing basis. These are unique “geo sector-specific” issues that must be managed, in addition to the typical power plant development and construction issues inherent in any energy project endeavor. Due to these challenges, the corresponding financing of geothermal projects must be carefully tailored to match these specific features.

Where Are the Investor Entry Points?

The key to financing geothermal energy projects is recognizing how the risk profile of a geothermal project varies over time as it is developed — from early-stage development, to drilling the wellfield, to construction and finally to plant operations — and then correctly matching the particular “investor type” and capital tranche with the project’s prevailing risk-return profile.

From a resource development standpoint, geothermal projects can broadly be described as “pre-drilling” and “post-drilling” (with various further permutations thereof). Pre-drilling is akin to many other early stage energy development projects and, as the name implies, references a project that has land control, permitting, environmental considerations, potentially some slim bore wells and/or temperature gradient holes and other such milestones complete or in process, but does not have actual production and injection wells drilled. Post-drilling similarly references a project with the wellfield completed and the drilling risk mitigated.

There is some degree of transition in terms of project maturation from pre- to post-drilling, and this in turn leads to various potential investor “entry points” (this will be later highlighted in the project financing discussion section). In addition, the risk profile of post-drilling projects also typically further improves with time as the project operates and the resource behavior is better understood. Such up and running projects, underpinned by stable resources, are the proverbial “gold standard” of geothermal projects and can therefore attract relatively low-cost, risk-conservative forms of capital at scale.

The Difficulty with Drilling

The drilling phase is typically an equity capital investment based on the risks, and is generally financed via “patient” strategic or private equity capital. It has been financed in the public markets also, but that avenue can lead to various challenges (discussed in Part II). Some developers may attempt to finance the first couple wells via individual high net-worth investors, similar to the Exploration and Production (E&P) world, however the challenges for this financing model include:

  1. The payback periods are generally not as fast compared to the oil & gas sector, which makes it more difficult to attract such capital on a relative basis.
  2. It is not as feasible to source this type of capital at the required scale in order to fund a complete project wellfield drilling program.

In some respects, the latter point is a function of the former, in that drilling just a few wells initially will typically not lead to revenue immediately, as it could for an oil/gas well drilled in a proven field with access to midstream gathering infrastructure and hydrocarbon markets to sell product. Rather, in the case of a geothermal project, not only does the entire wellfield need to be drilled and tested/proven, but the above-ground power plant also needs to be constructed and “synced” to the electric grid prior to any earnings from contractual power sales. This investment “paradigm” (slower payback times, capped upside tied to power purchase agreement (PPA) pricing etc.) simply does not create the type of economic incentives for the private investor pool that, in contrast, attracts them to fund smaller E&P drilling programs.

As the geothermal wellfield is drilled over time, there does come a stage when the drilling program — along with other components of the geothermal project such as an engineering, procurement and construction (EPC) contract, PPA, etc. — has adequately “matured” and the project is now able to attract senior secured debt capital. From a geothermal project financing perspective, debt investors typically look at the threshold of drilling work that needs to be completed in order for them to be comfortable in advancing the construction capital proceeds.

This threshold is often referred to as “percentage steam behind pipe” and specifically means the percentage of the current drilled capacity to the aggregate steam/geothermal fluid capacity that will be required for the entire power plant to run when it has entered commercial operations. This metric needs to be certified by the independent resource expert, and is carefully tracked by the lenders throughout the construction phase. It is sized to ensure that the lenders are made whole even in a “downside” production sensitivity case — and this critical characteristic is why this metric attracts highlighted lender scrutiny.

The construction lenders will also do a significant amount of diligence in conjunction with the resource expert consultant. This diligence is related to the projected reservoir performance over the project’s useful life, and they will structure in a variety of reserve accounts related to the wellfield and drilling in order to protect their position relative to ongoing project “resource risk.” Such reserve accounts can come in many different forms and “flavors.” and understanding the relative pros and cons of how they are structured and funded can be a critical financial lever that drives economics for a developer in the project financing negotiations phase. Since these geothermal financing deals are few and far between, an expert understanding of the relevant market comparables and deal features is vital for ensuring a successful transaction execution.

Stay tuned for Part II, where we will cover the permanent financing process for geothermal projects once they have completed the construction phase. We will also mention the tax financing process for US projects, as well as the public markets funding model. These are all important features of the geothermal finance markets, and understanding their implications can help geothermal developers and investors make optimal financing decisions for their projects.

Lead image: Geothermal plant via Shutterstock

RELATED ARTICLES

Renewable Energy Is Beginning To Power Africa

Andrew Burger, Contributor According to the International Energy Agency, sub-Saharan Africa will require more than $300 billion in investment to achieve universal electricity access by 2030. Committing more than $7 billion in U.S. government support ...

First Anniversary of The Balkan Floods Highlights Renewable Energy Market Opportunities

Ilias Tsagas, Contributor One year ago this month, severe flooding in Serbia, Bosnia-Herzegovina and Croatia killed 79 people, displaced about half a million and caused economic paralysis of the region. In the wake of these the catastrophic events, ...
Canadian Climate Goals

Canada Announces Weak Climate Target

Danielle Droitsch, NRDC Last week, Canada has announced its contribution to the global effort to reduce greenhouse gases by announcing its post-2020 target. The target announced today is off-track to the 80 percent cut by 2050 they committed to in...
Renewable Energy Stocks

What Drives Alternative Energy Stocks?

Harris Roen, The Roen Financial Report Alternative energy became a serious market player after the turn of the millennium. Since that time, solar, wind, smart grid and other alternative energy stocks have experienced both strong up and down trends. The forces at...
Sid Sinha, Senior Vice President at Marathon Capital LLC, has fifteen years of domestic and international experience in the energy industry across the midstream, power and upstream spectrum. At Marathon Capital, he focuses on the geothermal, E&P/m...

CURRENT MAGAZINE ISSUE

Volume 18, Issue 3
1505REW_C11

STAY CONNECTED

To register for our free
e-Newsletters, subscribe today:

SOCIAL ACTIVITY

Tweet the Editors! @megcichon @jennrunyon

FEATURED PARTNERS



EVENTS

Energy Storage USA 2015

Energy Storage USA is the leading conference in the United States focuse...

GEA Geothermal Energy Expo 2015

Every year, the Geothermal Energy Expo® hosts the world's largest ga...

National Geothermal Summit 2015

The Geothermal Energy Association (GEA) is pleased to be holding its fif...

COMPANY BLOGS

Net Zero Energy Efficient Buildings and Geothermal Heat Pumps

As the U.S. market for green building design and construction evolves, ...

Geothermal Earth Day Visual: Shaping Environmental Solutions

Earth day 2015 is an important point in history for the environment. Mem...

Environmentally friendly solutions for projects

geoAMPS joins the celebration of the worldwide observance of Earth Day o...

NEWSLETTERS

Renewable Energy: Subscribe Now

Solar Energy: Subscribe Now

Wind Energy: Subscribe Now

Geothermal Energy: Subscribe Now

Bioenergy: Subscribe Now  

 

FEATURED PARTNERS