The World's #1 Renewable Energy Network for News, Information, and Companies.
Untitled Document

Nevada Hydro Clears Up Interconnect Issues for 600-MW Project

The Nevada Hydro Co. filed a tardy Feb. 3 update with the Federal Energy Regulatory Commission that said it is making progress on a 600-MW pumped storage hydro project in California.

FERC in October 2012 issued a preliminary permit to Nevada Hydro to study the feasibility of the Lake Elsinore Advanced Pumped Storage Project, to be located on Lake Elsinore and San Juan Creek in Riverside, San Diego and Orange counties, Calif. A preliminary permit allows three years for feasibility work, with a license application then needed if the decision is to move the project forward.

The project would include about 32 miles of 500-kV transmission line connecting the project to an existing transmission line owned by Southern California Edison located north of the proposed project and to an existing San Diego Gas & Electric transmission line located to the south.

FERC on Jan. 29 chided the company about a late update report under the preliminary permit. The company said in the Feb. 3 update that since issuance of its preliminary permit, it has focused on two critical issues.

Connecting to the Grid

The company said it began the “arduous” interconnection process by filing an application with the California Independent System Operator (CAISO) in 2005 while the project was under review by the commission in its old docket. The application described a two-point connection, one to the north and one to the south. Although the company filed a single application and received a single CAISO queue position, the CAISO, SCE and SDG&E decided to bifurcate the application, requiring separate and unrelated connection processes for the northern and southern connections. This resulted in two independent sets of studies and two unrelated interconnection agreements, the company added.

It completed studies and interconnection agreement with SDG&E in 2008, but the studies and interconnection agreement with SCE were not completed until much later. In early 2012, the CAISO submitted for filing with the commission a proposed notice of termination canceling the Large Generator Interconnection Agreement (LGIA) among the company, SDG&E and CAISO. The CAISO claimed that the company breached the terms of the LGIA by failing to meet certain milestone dates. Within days of this filing, the CAISO also submitted for filing an unexecuted LGIA among the company, SCE and the CAISO. On the same day, SCE separately filed the identical LGIA under its own tariff.

In a May 2012 letter to SCE and the CAISO, the commission requested additional information on these filings, and the company, SCE, SDG&E, and the CAISO soon entered into commission–sponsored settlement proceedings to resolve various issues. It took all parties more than a year to resolve the issues, and the CAISO filed settlement documents in these dockets in mid–January 2014. When accepted by the commission, these filings assure the project its connections to the grid.

Assuring a Revenue Stream

Second only to the criticality on not being able to connect to the grid, is the issue of how to pay for construction of the project. The company’s representatives are actively participating in a number of regulatory proceedings in California relative to providing revenue sources for storage and firming resources. These proceedings include:

  • At the California Public Utilities Commission, proceedings focused on long term procurement, storage, renewable portfolio issues, tracking power purchase agreements and utility contracting opportunities, the outage and planned retirement of the San Onofre Nuclear Generating Station, and a number of proceedings specific to SDG&E and SCE.
  • At the CAISO, proceedings focused on transmission planning, grid management, reliability assessment, resource adequacy, generator interconnection and deliverability, local capacity requirements, flexible capacity requirements, aggregating pumping and generation, storage, generation plant modeling, and residual Order 1000 issues. ?The company is also considering discussing with the federal commission and stakeholders the potential for filing for federal rates under provisions of the Energy Policy Act of 2005.

In addition to these major tasks, the company said it also recently undertook the following tasks during this reporting period: continued discussions with the Cleveland National Forest relative to routing, environmental issues and processes; participated in proceedings at the California Energy Commission and the Western Electricity Coordinating Council; worked on the related Talega–Escondido/Valley–Serrano 500 kV Interconnect Project; and discussed with investors additional funding for the project.

This article was originally published on GenerationHub and was republished with permission.

Lead image: Hydropower dam via Shutterstock

Untitled Document

RELATED ARTICLES

States Already Seek To Delay Clean Power Plan

Andrew Harris, Bloomberg Fifteen states led by coal-rich West Virginia asked a federal court to stall Obama administration rules intended to c...

Global Renewable Energy Roundup: China, Kenya, Turkey, India Seeking More Renewables

Bloomberg News Editors China is being encouraged by three industry groups to double the nation’s solar-power goal for 2020 to make up for sh...

With Vast Amounts of Geothermal, Wind and Hydropower, Why No Solar In New Zealand?

James Ellsmoor, Contributor New Zealand has built an international brand on environmentalism and the great outdoors. So it is unsurprising that t...

HydroEvent.com launches for HydroVision International 2016

Gregory B. Poindexter HydroEvent.com, the one-stop location for all things related to the world’s largest hydro event, is up and running fo...

PRESS RELEASES

Array Technologies’ DuraTrack HZ v3 Continues to (R)evolutionize at SPI

Array Technologies, Inc. (ATI) prepares to showcase its recently launched tracking syst...

Appalachian's Energy Center assists counties with landfill gas to energy projects

The Appalachian Energy Center at Appalachian State University recently completed a proj...

Early Bird Registration Deadline for GRC Annual Meeting is This Week

The deadline for early-bird rates for registration for the biggest annual geothermal ev...

Redesigned HydroWorld.com Video Gallery

Hydropower news and information, and interesting promotional announcements are now avai...

FEATURED BLOGS

Transitioning to Net-Zero Living

Judith and Jeffrey adore living in Belfast, Maine – a quaint harbor town of Belfast, Maine. They previously res...

The True Cost of Electric Vehicles in Australia

In order to avoid increased congestion, further greenhouse warming and lessen Australia’s reliance on imported ...

The Coming Multi-trillion Dollar Energy Investment Drive

In coming years, a multi-trillion dollar low-emission energy investment drive will get underway. Three catalysts wil...

The Perfect Elevator Pitch

The elevator pitch is a concise statement that grabs attention and communicates value, ideally leading to a next step...

FINANCIAL NEWS

Barry Cassell is Chief Analyst for GenerationHub covering coal and emission controls issues, projects and policy. He has covered the coal and power generation industry for more than 24 years, beginning in November 2011 at GenerationHub and prior t...

CURRENT MAGAZINE ISSUE

Volume 18, Issue 4
1507REW_C11

STAY CONNECTED

To register for our free
e-Newsletters, subscribe today:

SOCIAL ACTIVITY

Tweet the Editors! @jennrunyon

FEATURED PARTNERS



EVENTS

Microhydro System Design and Installation Workshop

Participants will learn about: site assessment techniques including the ...

5th Annual Hydro Plant Maintenance

Join maintenance professionals to discuss the challenges in maintenance ...

2015 AREDAY Summit

The 12th Annual AREDAY Summit, August 8-13th in Snowmass Colorado. Engag...

COMPANY BLOGS

New coating extends cylinder life 8 times longer than traditional c...

Hydroelectric turbine systems operate in extremely harsh conditions. The...

Clean Energy Patents Maintain High Levels in First Quarter, Solar L...

U.S. patents for Clean Energy technologies from the first quarter of 201...

SAP for Utilities Blog

The Eventful Group produces the annual SAP for Utilites Conference ...

NEWSLETTERS

Renewable Energy: Subscribe Now

Solar Energy: Subscribe Now

Wind Energy: Subscribe Now

Geothermal Energy: Subscribe Now

Bioenergy: Subscribe Now  

 

FEATURED PARTNERS