The World's #1 Renewable Energy Network for News, Information, and Companies.

Nevada Hydro Clears Up Interconnect Issues for 600-MW Project

The Nevada Hydro Co. filed a tardy Feb. 3 update with the Federal Energy Regulatory Commission that said it is making progress on a 600-MW pumped storage hydro project in California.

FERC in October 2012 issued a preliminary permit to Nevada Hydro to study the feasibility of the Lake Elsinore Advanced Pumped Storage Project, to be located on Lake Elsinore and San Juan Creek in Riverside, San Diego and Orange counties, Calif. A preliminary permit allows three years for feasibility work, with a license application then needed if the decision is to move the project forward.

The project would include about 32 miles of 500-kV transmission line connecting the project to an existing transmission line owned by Southern California Edison located north of the proposed project and to an existing San Diego Gas & Electric transmission line located to the south.

FERC on Jan. 29 chided the company about a late update report under the preliminary permit. The company said in the Feb. 3 update that since issuance of its preliminary permit, it has focused on two critical issues.

Connecting to the Grid

The company said it began the “arduous” interconnection process by filing an application with the California Independent System Operator (CAISO) in 2005 while the project was under review by the commission in its old docket. The application described a two-point connection, one to the north and one to the south. Although the company filed a single application and received a single CAISO queue position, the CAISO, SCE and SDG&E decided to bifurcate the application, requiring separate and unrelated connection processes for the northern and southern connections. This resulted in two independent sets of studies and two unrelated interconnection agreements, the company added.

It completed studies and interconnection agreement with SDG&E in 2008, but the studies and interconnection agreement with SCE were not completed until much later. In early 2012, the CAISO submitted for filing with the commission a proposed notice of termination canceling the Large Generator Interconnection Agreement (LGIA) among the company, SDG&E and CAISO. The CAISO claimed that the company breached the terms of the LGIA by failing to meet certain milestone dates. Within days of this filing, the CAISO also submitted for filing an unexecuted LGIA among the company, SCE and the CAISO. On the same day, SCE separately filed the identical LGIA under its own tariff.

In a May 2012 letter to SCE and the CAISO, the commission requested additional information on these filings, and the company, SCE, SDG&E, and the CAISO soon entered into commission–sponsored settlement proceedings to resolve various issues. It took all parties more than a year to resolve the issues, and the CAISO filed settlement documents in these dockets in mid–January 2014. When accepted by the commission, these filings assure the project its connections to the grid.

Assuring a Revenue Stream

Second only to the criticality on not being able to connect to the grid, is the issue of how to pay for construction of the project. The company’s representatives are actively participating in a number of regulatory proceedings in California relative to providing revenue sources for storage and firming resources. These proceedings include:

  • At the California Public Utilities Commission, proceedings focused on long term procurement, storage, renewable portfolio issues, tracking power purchase agreements and utility contracting opportunities, the outage and planned retirement of the San Onofre Nuclear Generating Station, and a number of proceedings specific to SDG&E and SCE.
  • At the CAISO, proceedings focused on transmission planning, grid management, reliability assessment, resource adequacy, generator interconnection and deliverability, local capacity requirements, flexible capacity requirements, aggregating pumping and generation, storage, generation plant modeling, and residual Order 1000 issues. ?The company is also considering discussing with the federal commission and stakeholders the potential for filing for federal rates under provisions of the Energy Policy Act of 2005.

In addition to these major tasks, the company said it also recently undertook the following tasks during this reporting period: continued discussions with the Cleveland National Forest relative to routing, environmental issues and processes; participated in proceedings at the California Energy Commission and the Western Electricity Coordinating Council; worked on the related Talega–Escondido/Valley–Serrano 500 kV Interconnect Project; and discussed with investors additional funding for the project.

This article was originally published on GenerationHub and was republished with permission.

Lead image: Hydropower dam via Shutterstock

RELATED ARTICLES

US Capitol

Republicans and Democrats Back Bill to Level the Playing Field for Renewable Energy

Vince Font, Contributing Editor U.S. Senators Chris Coons and Jerry Moran are leading a bipartisan effort to reintroduce tax code legislation aimed at leveling the playing field for renewable energy investment. The Master Limited Partnerships Parity Act w...

Copperbelt Energy eyes Zambia's hydroelectric power market

Michael Harris

Zambian power distributor Copperbelt Energy Corp. Plc has reportedly spent US$3 million to perform feasibility studies for hydroelectric power development along Zambia's Luapula River.

Pope Francis

The Common Goals of the Pope and Clean Energy

Paul Stinson, EDF Pope Francis turned a keen eye toward the environment and the problem of climate change with his encyclical,“Laudato Si” (“Praised Be”). As a clean energy advocate, I’m heartened that Pope Francis recognizes the need t...
Tocardo Tidal Turbines

Commercial Tidal Energy Project in The Netherlands Will Cost $12.4 Million

Gregory B. Poindexter Tocardo Tidal Turbines announced it would install the largest tidal energy project in The Netherlands as well as the world's largest commercial tidal installation in a US$12.4 million project that includes an array of five ...
Barry Cassell is Chief Analyst for GenerationHub covering coal and emission controls issues, projects and policy. He has covered the coal and power generation industry for more than 24 years, beginning in November 2011 at GenerationHub and prior t...

CURRENT MAGAZINE ISSUE

Volume 18, Issue 3
1505REW_C11

STAY CONNECTED

To register for our free
e-Newsletters, subscribe today:

SOCIAL ACTIVITY

Tweet the Editors! @megcichon @jennrunyon

FEATURED PARTNERS



EVENTS

Outage Management for Power Plants

Building on this series’ success, the 14th Annual Outage Managemen...

SAP for Utilities

The SAP for Utilities conference is the most comprehensive SAP for Utili...

Mastering RETScreen® 4 for Clean Energy Project Analysis

Hands-on modeling class using RETScreen 4. Michael Ross designed this co...

COMPANY BLOGS

Environmentally friendly solutions for projects

geoAMPS joins the celebration of the worldwide observance of Earth Day o...

California Solar Installations Put 6 Gigawatts of Power Online

That’s according to figures from the California Independent System...

US Energy Grid Review Finds Needed Upgrades Would Allow More Solar,...

Yesterday (April 21) the U.S. Department of Energy released the first Qu...

NEWSLETTERS

Renewable Energy: Subscribe Now

Solar Energy: Subscribe Now

Wind Energy: Subscribe Now

Geothermal Energy: Subscribe Now

Bioenergy: Subscribe Now  

 

FEATURED PARTNERS