The World's #1 Renewable Energy Network for News, Information, and Companies.
Untitled Document

FERC Grants New Permit for 240-MW Alaska Tidal Energy Project

On Feb. 12, the Federal Energy Regulatory Commission approved a successive preliminary permit for Turnagain Arm Tidal Energy Corp. for a tidal energy project in Alaska.

In February 2013, Turnagain Arm Tidal Energy filed an application proposing to continue to study the feasibility of the Turnagain Arm Tidal Electric Generation Project. The project would be located on the Turnagain Arm of Cook Inlet and adjacent lands of the Kenai Peninsula Borough and the Municipality of Anchorage, Alaska.

The proposed project would consist of: an 8-mile-long tidal fence situated between Fire Island in the Municipality of Anchorage and Point Possession in the Kenai Peninsula Borough consisting of 24, 10-MW low-head, bi-directional horizontal bulb turbines for a total installed capacity of 240 MW; a 2-mile-long, 1-mile-wide water storage tank attached to the tidal fence; one control building/substation onshore near Anchorage and one near Point Possession; an 18-mile-long, 230-kV submerged transmission line connecting the tidal fence to the existing Chugach Electric Association substation at Point Woronzof in Anchorage and a new substation at Point Possession; and a 28-mile-long, 230-kV above-ground transmission line running parallel to an existing Homer Electric Association transmission line corridor and extending from Point Possession to the existing HEA Nikiski substation.

The proposed project would have an estimated average annual generation of 1,271,950 megawatt-hours.

The company previously held a three-year preliminary permit for this site that expired Jan. 31, 2013. During the term of the previous permit, it filed progress reports outlining its progress towards a license application. It also filed a Notice of Intent (NOI) to file a license application and a Pre-Application Document (PAD) for the project under the commission’s Integrated Licensing Process. This demonstrates that the company was diligently pursuing the requirements of its prior permit such that issuing a successive permit is reasonable, FERC noted.

The Hydropower Regulatory Efficiency Act of 2013 authorizes the commission to extend preliminary permit terms for not more than two additional years if it finds that the permittee has carried out activities under the permit in good faith and with reasonable diligence. “Given that the legislation suggests that five years is a sufficient maximum period to allow a potential applicant to prepare a development application, it seems appropriate, as a general matter, to limit to two years any subsequent permits that follow three-year initial permits,” it added. “Thus, as indicated below, this successive preliminary permit is granted for a 24-month term.”

This article was originally published on GenerationHub and was repubished with permission.

Lead image: Alaska via Shutterstock

Untitled Document

Get All the Renewable Energy World News Delivered to Your Inbox

Subscribe to Renewable Energy World or email newsletter today at no cost and receive the latest news and information.

 Subscribe Now

RELATED ARTICLES

First U.S. Grid-Connected OTEC Plant Goes Live on Hawaii

Andrew Burger Hawaii Governor David Ige on Aug. 21 joined executives from the Office of Ocean Naval Research (ONR), Makai Ocean Eng...

Makai Builds Ocean Thermal-Energy Demo Plant With U.S. Navy

Anna Hirtenstein, Bloomberg

Makai Ocean Engineering Inc. has built an ocean thermal-energy conversion demonstration plant in Hawaii.

Renewable Energy Gains Greater Opportunity in US Clean Power Plan

Elisa Wood After a year of being pummeled by opponents, Obama’s final carbon reduction plan emerged this week with an even stron...

Listen Up: Vampires Sucking Power from your House

The Energy Show on Renewable Energy World Here’s a nightmare for you: at night, when you’re asleep and you think things are quiet, there are vampires sucking p...

PRESS RELEASES

Canadian Solar Wins Five Solar Power Projects Totaling 185 MW in Brazil

These power projects were won under a 20-year Power Purchase Agreement (PPA) with the B...

$100 Off of 5-day Advanced PV Project Experience. Download a Topic Schedule.

Assemble, ground, energize, and commission a complete grid-tied SolarEdge system from s...

Former Australian Prime Minister Kevin Rudd talks politics of fear vs. politics of hope

Rudd, who led the Australian parliament from 2007 to 2010, told the Summit audience tha...

Intersolar AWARD „Solar Projects in India“ – Applications being accepted until September 18

The Intersolar AWARD in the category Solar Projects in India honors projects in the fie...

FEATURED BLOGS

Washington, DC Bridges the Solar Gap

The District of Columbia has enjoyed 15 years of strong economic growth. But prosperity is spread unevenly across the...

Sell Through Hypothesis

You first learned to hypothesize, or make educated guesses, in grade school science class. Now it’s time to ref...

Cronimet / THEnergy study: In solar for mines size does not always matter - Reducing CAPEX with energy efficiency and load shifting

Munich, September 2015. Mining companies are constantly gaining interest in solar solutions because frequently solar ...

Final Program Now Available for GRC Annual Meeting & GEA Geothermal Energy Expo

GRC Annual Meeting & GEA Geothermal Energy Expo - Final Program from

FINANCIAL NEWS

Barry Cassell is Chief Analyst for GenerationHub covering coal and emission controls issues, projects and policy. He has covered the coal and power generation industry for more than 24 years, beginning in November 2011 at GenerationHub and prior t...

CURRENT MAGAZINE ISSUE

Volume 18, Issue 4
1507REW_C11

STAY CONNECTED

To register for our free
e-Newsletters, subscribe today:

SOCIAL ACTIVITY

Tweet the Editors! @jennrunyon

FEATURED PARTNERS



EVENTS

International Energy and Sustainability Conference 2015

The fourth International Energy and Sustainability Conference will be he...

Microhydro System Design and Installation Workshop

Participants will learn about: site assessment techniques including the ...

5th Annual Hydro Plant Maintenance

Join maintenance professionals to discuss the challenges in maintenance ...

COMPANY BLOGS

Speaking Out For Hydro

In January, a columnist with Canada’s The Globe and Mail newspaper...

Years from now we may know the costs of the current El Niño

Hard science lets us know El Niño is real, but how much the weath...

Europe Leading Tidal Development, but US and Asia Catching Up

New analysis from market research and analysis firm Frost & Sullivan...

NEWSLETTERS

Renewable Energy: Subscribe Now

Solar Energy: Subscribe Now

Wind Energy: Subscribe Now

Geothermal Energy: Subscribe Now

Bioenergy: Subscribe Now  

 

FEATURED PARTNERS