Texas Renewable Energy Transmission Project Delayed by Bad Weather

Inclement weather is being blamed for preventing a perfect record for Texas’s competitive renewable energy zone (CREZ) transmission initiative by delaying a single transmission project in the central CREZ zone beyond the end-of-2013 target date for the projects’ completion.

The sole exception is the final project being built by Wind Energy Transmission Texas’s (WETT).

“There are a few remaining items to complete on Segment 7 (Sand Bluff to Bearkat) including utility coordination for final connections,” Wayne Morton, WETT general manager, told TransmissionHub Dec. 31Construction of the 29-mile line began Nov. 26, 2012, and is expected to be completed “within the next two weeks.” 

Meanwhile, WETT has completed construction and commissioning of the 37-mile Sand Bluff to Divide line. Both lines had been slated for completion earlier in the year but were delayed by foul weather, Morton said.

WETT, the third-largest CREZ developer by budget, was initially responsible for seven transmission lines and eight associated station and equipment projects. One equipment project, the Cottonwood capacitor bank project, was cancelled.

South Texas Electric Cooperative (STEC) completed its final project, the 76-mile Odessa to Bakersfield line, and turned control of the project over to the Lower Colorado River Authority (LCRA) for operation “well before Dec. 31,” Holly Gifford, STEC transmission project coordinator, told TransmissionHub Jan. 2.

STEC was initially responsible for three transmission lines, though the three projects were combined to form the Odessa to Bakersfield line and the 112-mile Bakersfield to Big Hill line, which was energized Aug. 31.

Oncor Electric Delivery Company energized the 70-mile West Krum to Anna line Dec. 30, an Oncor spokesperson told TransmissionHub Jan. 2. Oncor energized its penultimate project, the 110-mile Clear Crossing to Willow Creek line, on Dec. 18.

Construction began on the West Krum to Anna project on Aug. 10, 2012, and on the Clear Crossing to Willow Creek project on Jan. 21, 2012. Oncor was responsible for developing 27 transmission lines, the largest number of any CREZ developer, and had the largest current budget estimate of $1.9bn for the lines and 37 station and equipment projects.

Approved in 2008, the CREZ initiative saw 10 developers take part in what was designed as a transmission build-out to transport renewable energy from the wind-rich areas of the Texas Panhandle and West Texas to the load centers of Dallas-Ft. Worth, Austin, San Antonio, and beyond. The completed CREZ projects will eventually transmit 18,500 MW of wind energy.

The current estimated cost of the CREZ program, as reflected in the quarterly progress report issued by the Public Utility Commission of Texas (PUCT) Oct. 7, is $6.81bn, which represents an increase from the first revised figure of $6.56bn contained in the April 2011 report, but below the high of $6.95bn contained in the January 2012 report and a decline from the $6.82bn estimated in the July quarterly progress report.

There are several reasons for the variations, according to the report. The original estimate of $4.9bn, which resulted from the CREZ transmission optimization (CTO) study in 2008, was the outcome of “a planning exercise to develop multiple transmission plan scenarios from which to select the most cost effective and optimal scenario for execution,” according to the report. After the CTO was developed, an additional 70 projects were added, including three transmission lines comprising more than 600 miles of new transmission, and 67 associated facilities.

This article was originally published on TransmissionHub and was republished with permission.

Lead image: Transmission lines via Shutterstock

Untitled Document

RELATED ARTICLES

States Already Seek To Delay Clean Power Plan

Andrew Harris, Bloomberg Fifteen states led by coal-rich West Virginia asked a federal court to stall Obama administration rules intended to c...

Stolen Solar Panels and Sabotage A Challenge for Powering India With Renewable Energy

Anindya Upadhyay, Bloomberg Disappointment spread across Tarun Singh’s face when he saw that parts of his solar power microgrid in eastern India’...

Global Renewable Energy Roundup: China, Kenya, Turkey, India Seeking More Renewables

Bloomberg News Editors China is being encouraged by three industry groups to double the nation’s solar-power goal for 2020 to make up for sh...

With Vast Amounts of Geothermal, Wind and Hydropower, Why No Solar In New Zealand?

James Ellsmoor, Contributor New Zealand has built an international brand on environmentalism and the great outdoors. So it is unsurprising that t...

PRESS RELEASES

Array Technologies’ DuraTrack HZ v3 Continues to (R)evolutionize at SPI

Array Technologies, Inc. (ATI) prepares to showcase its recently launched tracking syst...

Appalachian's Energy Center assists counties with landfill gas to energy projects

The Appalachian Energy Center at Appalachian State University recently completed a proj...

Early Bird Registration Deadline for GRC Annual Meeting is This Week

The deadline for early-bird rates for registration for the biggest annual geothermal ev...

Redesigned HydroWorld.com Video Gallery

Hydropower news and information, and interesting promotional announcements are now avai...

FEATURED BLOGS

Transitioning to Net-Zero Living

Judith and Jeffrey adore living in Belfast, Maine – a quaint harbor town of Belfast, Maine. They previously res...

The True Cost of Electric Vehicles in Australia

In order to avoid increased congestion, further greenhouse warming and lessen Australia’s reliance on imported ...

The Coming Multi-trillion Dollar Energy Investment Drive

In coming years, a multi-trillion dollar low-emission energy investment drive will get underway. Three catalysts wil...

The Perfect Elevator Pitch

The elevator pitch is a concise statement that grabs attention and communicates value, ideally leading to a next step...

FINANCIAL NEWS

Carl Dombek, senior editor for TransmissionHub, is an award-winning journalist with nearly two decades of experience as a broadcast journalist on radio and TV, and as a writer for newspapers, magazines, and the Web. Prior to joining Transmissio...

CURRENT MAGAZINE ISSUE

Volume 18, Issue 4
1507REW_C11

STAY CONNECTED

To register for our free
e-Newsletters, subscribe today:

SOCIAL ACTIVITY

Tweet the Editors! @jennrunyon

FEATURED PARTNERS



EVENTS

Doing Business in South Africa – in partnership with GWEC, the Glob...

Wind Energy in South Africa has been expanding dramatically, growing fro...

Wind Operator Congress Europe

The UK’s only business-focused O&M event for the European wind...

Distributed Wind Energy Workshop

Description: Distributed wind energy is electricity that is produced for...

COMPANY BLOGS

Clean Energy Patents Maintain High Levels in First Quarter, Solar L...

U.S. patents for Clean Energy technologies from the first quarter of 201...

Koch Professor drops his Koch title, still makes same errors plus s...

The Koch Professor’s title isn’t the only thing that’s...

Fact Check: AWEA represents American wind power

The American Wind Energy Association (AWEA) is proud of its members for ...

NEWSLETTERS

Renewable Energy: Subscribe Now

Solar Energy: Subscribe Now

Wind Energy: Subscribe Now

Geothermal Energy: Subscribe Now

Bioenergy: Subscribe Now  

 

FEATURED PARTNERS