The World's #1 Renewable Energy Network for News, Information, and Companies.

Minn. Judge: Solar Beats Natural Gas for Utility Procurement

In what is being called an unprecedented decision, solar energy went head-to-head with natural gas in a competitive evaluation for utility resource planning — and solar came out on top.

Minnesota's renewable portfolio standard (RPS) calls for 25 percent of generation by 2025 from renewable energy sources. For Xcel, the state's largest electric utility, the rules are more aggressive at 31.5 percent by 2020. Last spring the state added a solar carve-out of 1.5 percent from solar by 2020, equivalent to about 450 MW of new solar capacity. The Minnesota Public Utilities Commission (PUC) determined that Xcel Energy demonstrated need for 150 MW of new electricity generation by 2017 (and possibly 500 MW by 2019) and directed the Office of Administrative Hearings (ALJ) to look at several proposals to decide "the most reasonable and prudent strategy" to meet Xcel's needs. Five proposals were received and accepted:

  • Xcel: three 215-MW natural-gas-fired, simple-cycle combustion turbine generators, two at its Black Dog facility in Burnsville, MN and two others at its Red River Valley facility in Hankinson, ND;
  • Calpine: a 345-MW combined cycle gas plant at its Mankato Energy Center, adding 290-MW of intermediate combined-cycle capacity and 55-MW of peaking capacity;
  • Geronimo Energy: 100-MW (AC) distributed solar capacity intermittent resource, spread across approximately 20 sites;
  • Great River Energy (GRE): proposed sale of capacity credits;
  • Invenergy: a 179-MW combustion turbine peaking facility at Cannon Falls and two 179-MW combustion turbines near Hampton, MN

Geronimo's proposed Aurora solar project encompasses roughly 20 different commercial-sized sites (2-10 MW) adding up to 100 MW, sized to offset roughly 20 percent of the existing load at each respective substation. Construction would begin in 2015 and all of the sites would be online by the end of 2016 to serve Xcel's capacity needs in 2017 (and to qualify for expiring investment tax credits). Two different pricing proposals were submitted under a 20-year PPA structure: one with a fixed monthly payment per kilowatt (kW) for capacity and an energy payment for all energy generated, and another as an energy-only payment bundling everything into a single dollars/MWh price. The total cost of Aurora is projected at $250 million.

Using computer models, the ALJ's administrative law judge Eric Lipman compared each proposal against each other, gauging cost savings, fuel consumption, pollutants emitted, and other factors, and then added a number of contingencies for mandated CO2 reductions, market pricing fluctuations for each energy source, and both short- and long-term demand projections — as well as the mandated RPS and solar carve-out. Lipman also added criteria to be "compatible with protecting the natural and socioeconomic environments, including human health." He also narrowed the scope to a short-term window, since Xcel could face a capacity deficit of 93 MW in 2017, and as much as 307 MW by 2019; calculations for demand beyond 2019 should revisited later, he said. (Here's the full PDF from the state's PUC.)

Thus, Lipman decreed that in the short-term "the greatest value to Minnesota and Xcel's ratepayers is drawn from selecting Geronimo's solar energy proposal" and possibly adding GRE's capacity credits. Geronimo's proposal, he declared, "when properly analyzed under either a LCOE or strategist modeling, is the lowest cost resource proposed," plus it represents the lowest risk against policy compliances.

Lipman himself noted the importance of this decision, calling it "an important turning point in Minnesota's energy resource planning process." For twenty-odd years the state has had policies supporting renewable energy sources, yet "nonrenewable energy sources always won the head-to-head cost comparisons. Not anymore." This time, he noted, "Geronimo entered this bidding process as the sole renewable technology and beat competing offerors on total life-cycle costs."

Responding to the ruling, Xcel issued a statement saying it appreciates the work of the ALJ toward resource acquisitions but it "disagree[s] with some of the findings and recommendation," and the company pledged to file a complete response once exceptions are filed with the commission, expected later this month. The PUC's final ruling should come a month or two after that.

Lead image: Illustration of boxer punch, via Shutterstock

RELATED ARTICLES

What Is the Value of Solar Energy + Storage?

Andrew Burger, Contributor What's the true, overall value of combined “behind the meter” energy storage plus solar PV deployment to U.S. power utilities and their customers? That's the big question facing stakeholders in Hawaii and other U.S. states ...

Listen Up: The Solar Maintenance Myth

The Energy Show on Renewable Energy World Why are rooftop solar systems so reliable? First, because the solar panels themselves have zero moving parts, use tempered glass and anodized aluminum (better than most windows and skylights), and are covered by a 25 year m...
Solar panels

New Tool Helps Utilities Manage the Rapidly Growing Community Solar Market

Vince Font, Contributing Editor Community solar projects are among the fastest growing solar segments in the U.S with some estimates forecasting that community solar initiatives will be responsible for the addition of 500 MW (megawatts) of annual capacity...
Pope Francis

A 9-Minute Guide To Pope Francis’ Encyclical on Climate Change

Jim Lane, Biofuels Digest Pope Francis issued Laudato si’ (Praise Be to You) On the care for our common home, his second encyclical, concerning Catholic doctrine with respect to climate change, consumerism, and development.
Jim is Contributing Editor for RenewableEnergyWorld.com, covering the solar and wind beats. He previously was associate editor for Solid State Technology and Photovoltaics World, and has covered semiconductor manufacturing and related industries, ...

CURRENT MAGAZINE ISSUE

Volume 18, Issue 3
1505REW_C11

STAY CONNECTED

To register for our free
e-Newsletters, subscribe today:

SOCIAL ACTIVITY

Tweet the Editors! @megcichon @jennrunyon

FEATURED PARTNERS



EVENTS

NFMT Orlando

NFMT Orlando is a trade show and educational conference for facility pro...

Green Sports Alliance Summit

The annual Green Sports Alliance Summit is the world’s largest and...

SAP for Utilities

The SAP for Utilities conference is the most comprehensive SAP for Utili...

COMPANY BLOGS

Five Reasons Why Solar is a Safe Investment

Nothing is certain but death and taxes. But most of us are confident tha...

Five Ways GreenLancer Creates High Quality Solar Designs

High quality solar designs don’t have to take weeks to get back to...

How To Ace A Presentation

Most sales professionals are asked to give presentations from time to ti...

NEWSLETTERS

Renewable Energy: Subscribe Now

Solar Energy: Subscribe Now

Wind Energy: Subscribe Now

Geothermal Energy: Subscribe Now

Bioenergy: Subscribe Now  

 

FEATURED PARTNERS