FERC Adopts New California Fast Track Interconnection Rules Nation-wide

California did it again — it led the nation on a key environmental issue. In this case, FERC (the Federal Energy Regulation Commission) adopted key aspects of California’s new interconnection rules for small wholesale energy projects like solar and small hydro. The Fast Track process, which FERC largely adopted, is a dramatically cheaper and faster interconnection process for qualifying small projects, so this change represents a major improvement with nation-wide impacts.

FERC adopted a number of changes in the Small Generator Interconnection Procedures (SGIP), three of which I’ll focus on here: 1) utilities must provide a $300 Pre-Application Report to requesting parties, which includes important information for judging the cost and feasibility of interconnection of the site at issue; 2) raise the minimum size for Fast Track from 2 MW up to 5 MW; 3) change the 50 percent minimum load rule to 100 percent, which effectively doubles the size of projects that can pass Fast Track.

All of these changes were first adopted by California in its interconnection reform process for the state-jurisdictional Rule 21 procedure in 2011 and 2012. I was heavily involved, as co-lead, in this reform process in California on behalf of my client, the Clean Coalition. We wrote much of the language that was adopted in the requirements for the Pre-Application Report and also influenced many other features of these reforms in what became a lengthy settlement process.

The Clean Coalition was also active in the FERC reform process, and I and my client were very happy to see FERC adopt California’s new rules almost unchanged. Kudos  also goes to the Interstate Renewable Energy Council (IREC) and the Solar Energy Industries Association (SEIA) in these efforts.

So what do these changes mean? Let’s go through each of the three major changes one by one.

Pre-Application Report

The new $300 report allows developers to obtain the following information if it is “readily available” to the relevant utility:

  1. Total capacity and available capacity of the facilities that serve the Point of Interconnection;
  2. Existing and queued generation at the facilities likely serving the Point of Interconnection;
  3. Voltage of the facilities that serve the Point of Interconnection;
  4. Circuit distance between the proposed Point of Interconnection and the substation likely to serve the Point of Interconnection (Substation);
  5. Number and rating of protective devices and number and type of voltage regulating devices between the proposed Point of Interconnection and the Substation;
  6. Number of phases available at the proposed Point of Interconnection;
  7. Limiting conductor ratings from the proposed Point of Interconnection to the Substation;
  8. Peak and minimum load data; and
  9. Existing or known constraints associated with the Point of Interconnection.

These combined data give the developer a pretty good idea of the feasibility and cost of interconnecting under Fast Track or other procedures because the costs of interconnecting under Fast Track are generally fixed. For example, in California, the interconnection request fee, which includes the Initial Review, is $800. Supplemental review is $2,500. These fees are far lower than the $50,000 plus $1,000 per megawatt study fee under the default cluster study process, for example.

The benefit of the new Pre-Application Report option is to provide a very low cost tool for developers to figure out if a site is suitable for their solar, wind, etc., project. Previously, developers would have to submit an interconnection request and go through the process to find out. Reports from developers in California indicate that, so far, the new Pre-Application Report option is working quite well.

Increase Fast Track Eligibility from 2 MW up to 5 MW

FERC increased Fast Track eligibility up to 5 MW, based on the proximity to substations and line size, as described in the following chart. This is also a major improvement, particularly when we consider the change discussed in the next section. The eligibility threshold changes adopted by FERC are in fact better than those adopted by California (which allows up to only 3 MW), so the reform process is an ongoing dance of reforms between the state and federal levels. It is likely that California will adopt the table below before too long.

Change Minimum Load Screen from 50 to 100 Percent 

Under the former interconnection procedure, “Screen 2” was the bane of Fast Track applicants’ efforts to interconnect. Screen 2 required that a project not exceed 15 percent of the peak load on the line section at issue. A line section is the next size down from the circuit level, which itself is the next structure down from the substation level. The 15% rule was adopted as an approximation of 50 percent of the minimum load on the line section. “Load” refers to how much power is being drawn from customers.  The idea behind this rule was that, in order to avoid backflow above the line section at issue, utilities should play it safe and limit the interconnection size of projects that feed power back onto the grid to half of the minimum load. 

In practice, this meant, for example, that a line section that saw only 1 MW of minimum load at, say 2:00 a.m., could interconnect 500 kW under Screen 2. California regulators, utilities and stakeholders agreed that this rule could be relaxed a bit. The California Public Utilities Commission (CPUC), which regulates utilities and state-jurisdictional interconnection procedures under Rule 21, agreed to adopt a 100 percent minimum load rule instead of the 50 percent rule, as part of the new supplemental review procedure.

In effect, this change allows projects at least twice as large as before to interconnect under Fast Track. Combined with the change to the 2 MW size threshold limitation, developers can now interconnect projects up to 5 MW in far more situations than previously possible. It wasn’t enough to simply allow up to 5 MW under the size threshold if a project would then be rejected for failing to meet the minimum load screen. And good for FERC for recognizing this. 

The New Reforms in Action

I have had the pleasure of being the first to successfully navigate California’s new Rule 21 Fast Track process. My client, the Blue Sky Sustainable Ranch, in the Cuyama Valley in northern Santa Barbara County, obtained interconnection permission from PG&E for 1 MW and a 1.5 MW under the new Rule 21 Fast Track in late 2013. Without the reforms that the CPUC implemented in early 2012, we would not have been able to gain this permission because we would have exceeded the 15 percent maximum load rule even with much smaller projects. 

The renewables revolution is ramping up in California and around the country and regulators like the CPUC and FERC will need to be vigilant in order to keep ahead of the curve on issues like interconnection. 

Lead image: California via Shutterstock

Untitled Document

Get All the Renewable Energy World News Delivered to Your Inbox - FREE!

Subscribe to Renewable Energy World Magazine and our award-winning e-Newsletter to stay up to date on current news and industry trends.

 Subscribe Now


US Senate Democrats Unveil Energy Bill That Restores PTC and Extends ITC

Brian Eckhouse, Bloomberg Senate Democrats unveiled a bill that would provide more tax credits for renewable energy while killing some tax ince...

US, China Solar PV Players Team Up, Invest $100MM in Chile, Uruguay and Japan

Andrew Burger Private equity infrastructure specialist Hudson Clean Energy Partners and Hong Kong-based independent power producer ...

CEO Gilles: Challenge in Geothermal is to 'Level Playing Field' with Wind, Solar

Jennifer Delony The current challenge for the geothermal energy industry is what U.S. Geothermal CEO Dennis Gilles calls “leveling th...

NRG Energy to Form Renewable Unit, Sell Wind Assets to Yieldco

Mark Chediak and Matthew Monks, Bloomberg NRG Energy Inc., the worst-performing member of the S&P 500 Utilities Index this year, said it will form a renewa...


Solar Power World Ranks Florida Solar One a Top 400 Solar Installer

Florida Solar One, a Miami Fort Lauderdale solar contractor is ranked among the top sol...

US Solar Institute Chosen for Military Solar Training at Patrick Air Force Base

In August 2015, the Air Force chose The US Solar Institute (USSI) for a specialized sol...

Canadian Solar Signs Agreement with Mashiki Town and Kumamoto Prefecture to Build 47 MW Solar Plant in Japan

Canadian Solar Signs Agreement for 47 MW Solar Plant

NC State University Installs Student-Funded Spotlight Solar Structure to Drive Awareness and Adoption of Clean Energy

North Carolina State University (NC State) will today showcase its commitment to clean ...



Geothermal Visual: GEA, Clean Energy Organizations Tell Congress: We Need Tax Extenders 'As Soon As Possible'

In a letter dated Oct. 5, over 580 signatories representing clean energy industries, including Geothermal Energy Asso...

Why the Solar PV Industry Should Love Geothermal Heat Pumps Part 3

It’s a marriage made in heaven: Solar PV and Geothermal Heat Pumps Part 3 of a 6-Part Series Geothermal Heat ...

Beyond Utility 2.0: Part 4 “Next Steps”

Principles, Structure, and Policies of Energy Democracy Energy democracy can best be described as an electricity sy...



Volume 18, Issue 4


To register for our free
e-Newsletters, subscribe today:


Tweet the Editors! @jennrunyon



Successfully Integrating Solar: A Proactive Approach

•      What does the increasing solar penetrati...

Canadian Solar Inverters Webinar

Canadian Solar is proud to be hosting two free webinars in October! The ...

JuiceBox Energy Certified Installer Class

JuiceBox Energy is rapidly building out its national certified installer...


The Grab Bag Rides Again

Pregame When I was sports editor for the college newspaper, I wrote a co...

How To Speak, How To Listen

As sales professionals, effective communication is paramount to our succ...

Get In The Habit

We all develop habits throughout our lives. Sometimes they’re bene...


Renewable Energy: Subscribe Now

Solar Energy: Subscribe Now

Wind Energy: Subscribe Now

Geothermal Energy: Subscribe Now

Bioenergy: Subscribe Now