The World's #1 Renewable Energy Network for News, Information, and Companies.
Untitled Document

Securing the World’s Largest Wind Turbine

At 7 megawatts (MW), Samsung Heavy Industries' S7.0-171 is the world's largest offshore wind turbine. The 196-metre tall structure is being installed 20 metres offshore in Fife, Scotland, with a connecting walkway to enable visitors to get up close to the structure.

FoundOcean has been contracted to secure the foundations for the turbine. Beaton Sutherland, Project Manager, explains how this project differs from the other offshore projects the company has worked on. “There are two main differences: Our equipment and personnel are based onshore at the dock side, with the grout lines running along a temporary platform to the piles, rather than being on a vessel. Secondly, this foundation has been designed to use pilot caissons around the piles. Everything else remains the same.”

And by the same token, Sutherland is referring to the factors that can influence how smoothly the project runs.

“The weather still affects all the contractors on site – if the wind is too high then the crane which moves hoses, people, and steel around the site cannot operate.”

The Samsung turbine is being housed on a four-legged steel jacket foundation. A number of characteristics are taken into consideration when designers recommend which foundation type is most appropriate, including turbine size, water depth, and soil properties.

In this case, although the water depth is negligible, the seabed is rocky and the turbine is very large – the nacelle alone weighs 500 tonnes.

A technique called rock socket grouting will be used for the project, ensuring a solid connection for the piles in the rock bed. When piles cannot be hammered, a socket is drilled in the seabed, resulting in a hole slightly larger than the pile that will be placed. This is to allow for fabrication tolerances and verticality of the socket. It also reduces noise, a key factor when so close to shore.

The installation of the jacket itself will happen when the substructure arrives onsite this autumn. Each of its four legs has a stab-in connection that sits inside the pile, a tried-and-tested design that has been used in other wind farms including Ormonde and Thornton Bank. Once the jacket is craned into position, grout will be injected into the stab-in leg connections and fill the pile annuli.

The walkway from the shore to the turbine foundation will be secured using the same procedure.

Innovation for Cost Saving

With any developing industry comes innovation, whether it is product-, service- or supply chain-related. The same can certainly be said for grouting operations for the offshore renewables sector, with the introduction of new materials, faster mixing equipment, and safer procedures.

The ultra-high strength (UHS) materials used in offshore wind, especially for monopile foundations, do not easily lend themselves to the high delivery rates of ordinary Portland cement (OPC) used in the majority of grouted connections, seen mostly in the oil & gas sector. This is due to the two different methods of mixing grout: batch-mixing for UHS materials and continuous, and silo-fed mixing for OPC-based materials.

Damien Murphy, Technical Director at FoundOcean, explained how the cost savings are achieved. “We got rid of the inefficiency of the one-step-at-a-time batch mixing grouting process. The new configuration means that we are able to perform simultaneously the three key functions of grouting: loading material, mixing it, and pumping grout to the structure.” He continues, “This means we can produce larger volumes of grout at a time and annuli can be filled quicker. Our clients get the benefit of much faster UHS grouting times, which ultimately leads to a reduction on the number of days offshore.”

Ultra-high strength material’s properties lend themselves well to the project requirements, including:

  • Low heat of hydration, thus eliminating the risk of thermal cracking
  • Rapid strength build-up even at low temperatures to support increased installation rates
  • 28-day compressive strengths of 140 MPa
  • Pumpability in temperatures as low as 0ºC, extending the available installation season

Finally, and arguably the most important attribute, autogenous shrinkage is a factor which, when present, is proven to cause cracking in high-strength concrete connections.

The Winds of Change

In the next five years, an estimated 4,000 new fixed structures are scheduled to be installed in the North Sea alone. This is mainly due to the upsurge in offshore wind activity associated with Round 2 and Round 3 projects.

Once consent is granted, all members of the supply chain will need to work together to make the installation process run efficiently: from tier two suppliers all the way to wind farm developers. This is happening to some extent already – but more joined-up project planning and collaboration across companies will be the real source of revolutionary innovation.

FoundOcean is already in talks with its suppliers to develop new high and ultra-high strength materials that are able to be mixed using a recirculating jet mixer-method, potentially quadrupling current grout output rates.

An interesting concept and one that the company would not expand on – yet.

Lead image: offshore wind farm via Shutterstock

Untitled Document

RELATED ARTICLES

Global Renewable Energy Roundup: China, Kenya, Turkey, India Seeking More Renewables

Bloomberg News Editors China is being encouraged by three industry groups to double the nation’s solar-power goal for 2020 to make up for sh...

With Vast Amounts of Geothermal, Wind and Hydropower, Why No Solar In New Zealand?

James Ellsmoor, Contributor New Zealand has built an international brand on environmentalism and the great outdoors. So it is unsurprising that t...

GE low wind turbines make debut in France

Kelvin Ross

A new wind farm in France will be the first in the country to deploy GE’s 2.75-120 wind turbines.

Unlikely Allies in North Carolina Clean-Energy Fight

Mark Drajem, Bloomberg With North Carolina’s renewable energy mandate under assault from Republican legislators, green groups seeking to sav...

PRESS RELEASES

Array Technologies’ DuraTrack HZ v3 Continues to (R)evolutionize at SPI

Array Technologies, Inc. (ATI) prepares to showcase its recently launched tracking syst...

Appalachian's Energy Center assists counties with landfill gas to energy projects

The Appalachian Energy Center at Appalachian State University recently completed a proj...

Early Bird Registration Deadline for GRC Annual Meeting is This Week

The deadline for early-bird rates for registration for the biggest annual geothermal ev...

Redesigned HydroWorld.com Video Gallery

Hydropower news and information, and interesting promotional announcements are now avai...

FEATURED BLOGS

Transitioning to Net-Zero Living

Judith and Jeffrey adore living in Belfast, Maine – a quaint harbor town of Belfast, Maine. They previously res...

The True Cost of Electric Vehicles in Australia

In order to avoid increased congestion, further greenhouse warming and lessen Australia’s reliance on imported ...

The Coming Multi-trillion Dollar Energy Investment Drive

In coming years, a multi-trillion dollar low-emission energy investment drive will get underway. Three catalysts wil...

The Perfect Elevator Pitch

The elevator pitch is a concise statement that grabs attention and communicates value, ideally leading to a next step...

FINANCIAL NEWS

Jim Bell began his engineering career in heavy civil engineering and highway construction at Wimpey Construction Group. He then moved to the offshore division of Wimpey Laboratories. Jim took the role of Managing Director at FoundOcean in 2005, wh...

CURRENT MAGAZINE ISSUE

Volume 18, Issue 4
1507REW_C11

STAY CONNECTED

To register for our free
e-Newsletters, subscribe today:

SOCIAL ACTIVITY

Tweet the Editors! @jennrunyon

FEATURED PARTNERS



EVENTS

Doing Business in South Africa – in partnership with GWEC, the Glob...

Wind Energy in South Africa has been expanding dramatically, growing fro...

Distributed Wind Energy Workshop

Description: Distributed wind energy is electricity that is produced for...

2015 AREDAY Summit

The 12th Annual AREDAY Summit, August 8-13th in Snowmass Colorado. Engag...

COMPANY BLOGS

Clean Energy Patents Maintain High Levels in First Quarter, Solar L...

U.S. patents for Clean Energy technologies from the first quarter of 201...

Koch Professor drops his Koch title, still makes same errors plus s...

The Koch Professor’s title isn’t the only thing that’s...

Fact Check: AWEA represents American wind power

The American Wind Energy Association (AWEA) is proud of its members for ...

NEWSLETTERS

Renewable Energy: Subscribe Now

Solar Energy: Subscribe Now

Wind Energy: Subscribe Now

Geothermal Energy: Subscribe Now

Bioenergy: Subscribe Now  

 

FEATURED PARTNERS