Ontario Loses WTO Appeal: What Happens Next?

After a lengthy appeal process, the WTO recently ruled in favour of Japan and the European Union in a case over Ontario's domestic content requirements (DCR) for renewable energy projects under the province's FIT Program. In light of this decision, the DCR, which mandate that project developers procure 50-60 percent of the value of their installations from equipment assembled or manufactured in Ontario, are now effectively illegal under the multilateral WTO agreement. As a result, Ontario's provincial government, which oversees the administration of the FIT Program, is now in a position in which it must make a policy choice which will likely have far reaching political and economic consequences as well as a significant impact on the province's renewable energy industry.

While it is expected that existing FIT contracts which mandate domestic content will remain in force, there will likely be changes to these requirements for future rounds of contract awards. ClearSky Advisors, as a close follower of the Canadian renewable energy industry, has outlined several scenarios which may come about as a result of the recent WTO decision:

Do Nothing: Although this is an unlikely scenario, the Ontario government could potentially decide to disregard the WTO ruling and continue to impose domestic content requirements on renewable energy projects. By doing so Canada would force the EU and Japan to move to place trade sanctions against Canada which could take the form of countervailing duties or fines. This option is unlikely due to the potential to disrupt international relations, especially in the face of Canada’s ongoing free trade negotiations with the EU as well as with Japan as a part of the Trans-Pacific Partnership.

Two-Tiered Pricing: Under a two-tiered pricing system Ontario would pay a higher price for electricity generated with domestically manufactured equipment than for electricity generated with foreign equipment. The intent of this option is the same as that of mandatory domestic content which would likely make this option an issue under WTO rules.

Priority Points and MUSH: An alternative to the two-tiered system could involve the Ontario government redesigning the FIT regulations to increase the number of projects awarded to municipal, university, school and hospital (MUSH) applicants. Such contracts would fall under public procurement for which DCR are less likely to be deemed in conflict with WTO rules. In order to do this the government may have to adjust the priority points to more strongly favour MUSH project applicants to ensure continued demand for domestically manufactured equipment.

Abandon DCR: Completely abandoning any type of domestic content requirements, although a more likely scenario than doing nothing, is ultimately less likely than favouring the MUSH sector. Abandoning DCR would likely be perceived as politically unattractive by the Ontario government since job creation and economic growth were two of the main goals of the province’s FIT program.

Impact for 2013 Forecast: Applications have already been submitted for the next round of Ontario’s smallFIT contracts, as well as for the remaining 7 MW of microFIT contracts from the current round of awards. Depending on the OPA’s response to the WTO ruling, there may be delays in awarding future rounds of contracts which will have a negative impact on installations in Ontario through 2013.

If, for example, microFIT contracts are delayed by three months, ClearSky Advisors expects that up to 10 MW of installations which would have occurred in 2013 will be pushed in 2014. Accordingly, if the 200 MW of smallFIT contracts which are scheduled to be announced in June are delayed by three months it is expected that none of this capacity will be installed in 2013.

Moving forward, it will be important for stakeholders in the Ontario renewable energy industry to stay well-informed of the OPA’s progress in awarding new contracts and to keep any delays in mind when forecasting business needs through the end of 2013 and beginning of 2014. Manufacturers with facilities within Ontario will also be best served if the government chooses to increase the number of projects awarded to MUSH hosts, and because of this, manufacturers should ensure that the relevant government agencies are aware of this preference.

Untitled Document

RELATED ARTICLES

States Already Seek To Delay Clean Power Plan

Andrew Harris, Bloomberg Fifteen states led by coal-rich West Virginia asked a federal court to stall Obama administration rules intended to c...

Stolen Solar Panels and Sabotage A Challenge for Powering India With Renewable Energy

Anindya Upadhyay, Bloomberg Disappointment spread across Tarun Singh’s face when he saw that parts of his solar power microgrid in eastern India’...

Suntech Parent Company Buys Majority Share of US-based Suniva

Ehren Goossens Shunfeng International Clean Energy Ltd., the Hong Kong-based solar company controlled by billionaire Zheng Jianming,...

Sunrise in Pakistan as the Country Delves into Solar PV

Robert Harker Pakistan has joined the list of countries that are exploring solar power as a means to bridge critical energy generat...

PRESS RELEASES

Canadian Solar Announces Partnership in 200 MW Tranquility Solar Power Project

Recurrent Energy signed an agreement with Southern Power to partner on the Tranquility ...

AWS Truepower Announces Major Expansion of its Due Diligence Team in Response to Growing Market Demand

AWS Truepower, an international leader in wind and solar energy consulting and engineer...

20 days to GRC Annual Meeting & GEA Geothermal Energy Expo

The Geothermal Resources Council (GRC) has announced that it is only 20 days to go to t...

Array Technologies’ DuraTrack HZ v3 Continues to (R)evolutionize at SPI

Array Technologies, Inc. (ATI) prepares to showcase its recently launched tracking syst...

FEATURED BLOGS

NATiVE Recognized for Excellence at 2015 Greater Austin Business Awards

NATiVE Recognized for Excellence at 2015 Greater Austin Business Awards NEWS RELEASE AUSTIN, Texas – Aug. 27...

Solar Energy Means Jobs, Savings, and a Low-Cost Future [infographic]

There are a lot of utility-sponsored legislative and regulatory attacks on solar energy lately, and we put together t...

How To Get People To Do Stuff

It’s no secret that psychology and sales go hand in hand. If you understand the principles of human psychology ...

Get In The Groove

When we talk about strategies for boosting productivity, we often overlook the fact certain projects lend themselves ...

FINANCIAL NEWS

Mark Bissegger is an Analyst with ClearSky Advisors where he has focused on market research and forecasting for the solar PV industry. His work contributes to ClearSky Advisors' Global Emerging PV Markets Service as well as to the Canada Solar PV ...

CURRENT MAGAZINE ISSUE

Volume 18, Issue 4
1507REW_C11

STAY CONNECTED

To register for our free
e-Newsletters, subscribe today:

SOCIAL ACTIVITY

Tweet the Editors! @jennrunyon

FEATURED PARTNERS



EVENTS

Intersolar North America 2016

Exhibition: July 12 - 14, 2016; Conference: July 11 - 13, 2016 Intersola...

Intersolar South America 2015

Exhibition and Conference: September 1-3, 2015 Intersolar South America ...

Intersolar Europe 2016

Exhibition: June 22-24, 2016; Conference: June 21-22, 2016 Intersolar Eu...

COMPANY BLOGS

How To Recruit An Internal Ally

When you’re collecting information for a proposal, the person with...

The Proof Is Not Always In The Pudding

One of the best ways to turn a skeptical prospect into a buyer is to giv...

Pushing Beyond The Cushion

Efficiency projects are all too often viewed as “optional” o...

NEWSLETTERS

Renewable Energy: Subscribe Now

Solar Energy: Subscribe Now

Wind Energy: Subscribe Now

Geothermal Energy: Subscribe Now

Bioenergy: Subscribe Now  

 

FEATURED PARTNERS