NextEra Chops Blythe Solar Project Proposal Amid Switch to Solar PV

NextEra has submitted a revised proposal for its massive Blythe Solar Power Project in California, aiming to shrink the project by more than half from its initial 1,000-MW goal as it shifts the project to solar PV technology.

NextEra acquired the Blythe project in June 2012 from original owner Solar Millennium, which had just filed for bankruptcy. It then proposed to switch the design from concentrated solar thermal to solar photovoltaic (PV) technology which had clearly become more cost-compelling, both from a procurement standpoint and in project scope (eliminating several power blocks and towers, reducing infrastructure requirements and water usage, and easing environmental impacts).

In a new filing with the California Energy Commission (CEC), the company said it is evaluating both thin-film and polycrystalline solar PV modules, as well as fixed-tilt and single-axis tracking systems (or some combination of either), but hasn't yet decided what PV technology or vendors it might use. It did, however, list two types of "typical panels" for each case, specifically First Solar's SF Series 3 cadmium-telluride (CdTe) panels and Yingli Green Energy's YGE 300 Series polycrystalline panels. First Solar had previously been suggested as a potential supplier to the Blythe project, largely because of its ability to provide such a large amount of panels. First Solar already is working with NextEra on its 550-MW Desert Sunlight project in California.

Instead of four units with 250-MW nominal capacity, NextEra now proposes three phases of 125-MW (AC) units using solar PV technology, plus a fourth unit of 110 MW (AC). All four units would share access/maintenance roads and a 230-kV transmission line.

If approved, the first phase of construction at Blythe could begin in mid-2014, with the entire project taking four years to complete. NextEra also pegs a preliminary number on capital cost of the project ($1.1 billion), materials and supply purchases ($15 million), construction payroll ($173 million), and annual O&M ($1.55 million).

The Blythe solar project: original boundary for solar thermal in orange, and modified PV proposal in black. (Source: CEC filing)

RELATED ARTICLES

Solar panels

New Tool Helps Utilities Manage the Rapidly Growing Community Solar Market

Vince Font, Contributing Editor Community solar projects are among the fastest growing solar segments in the U.S with some estimates forecasting that community solar initiatives will be responsible for the addition of 500 MW (megawatts) of annual capacity...
Pope Francis

A 9-Minute Guide To Pope Francis’ Encyclical on Climate Change

Jim Lane, Biofuels Digest Pope Francis issued Laudato si’ (Praise Be to You) On the care for our common home, his second encyclical, concerning Catholic doctrine with respect to climate change, consumerism, and development.

Intersolar Europe 2015: Spirits Up, Stats Down

William P. Hirshman, Contributor Intersolar Europe, billed at the world’s leading exhibition for the solar industry, is indeed big. But Intersolar Europe 2015, one of five Intersolar-branded gatherings around the globe each year, was not as large as the an...
US Capitol

Republicans and Democrats Back Bill to Level the Playing Field for Renewable Energy

Vince Font, Contributing Editor U.S. Senators Chris Coons and Jerry Moran are leading a bipartisan effort to reintroduce tax code legislation aimed at leveling the playing field for renewable energy investment. The Master Limited Partnerships Parity Act w...
Jim is Contributing Editor for RenewableEnergyWorld.com, covering the solar and wind beats. He previously was associate editor for Solid State Technology and Photovoltaics World, and has covered semiconductor manufacturing and related industries, ...

CURRENT MAGAZINE ISSUE

Volume 18, Issue 3
1505REW_C11

STAY CONNECTED

To register for our free
e-Newsletters, subscribe today:

SOCIAL ACTIVITY

Tweet the Editors! @megcichon @jennrunyon

FEATURED PARTNERS



EVENTS

NFMT Orlando

NFMT Orlando is a trade show and educational conference for facility pro...

Green Sports Alliance Summit

The annual Green Sports Alliance Summit is the world’s largest and...

SAP for Utilities

The SAP for Utilities conference is the most comprehensive SAP for Utili...

COMPANY BLOGS

Five Ways GreenLancer Creates High Quality Solar Designs

High quality solar designs don’t have to take weeks to get back to...

How To Ace A Presentation

Most sales professionals are asked to give presentations from time to ti...

More Middle-Class Massachusetts Residents Are Going Solar

Massachusetts is known for the Pilgrims, Boston cream pie and its excell...

NEWSLETTERS

Renewable Energy: Subscribe Now

Solar Energy: Subscribe Now

Wind Energy: Subscribe Now

Geothermal Energy: Subscribe Now

Bioenergy: Subscribe Now  

 

FEATURED PARTNERS