The World's #1 Renewable Energy Network for News, Information, and Companies.

IRS Defines Start of Construction for the Production Tax Credit

The Internal Revenue Service explained today what developers must do this year to be considered to have started construction of new renewable energy projects.

The IRS adopted roughly the same definition for start of construction as under the Treasury cash grant program. 

Wind, geothermal, biomass, landfill gas, incremental hydroelectric and ocean energy projects that are under construction by December 2013 will qualify for 10 years of production tax credits on the electricity output or an investment tax credit upon project completion for 30 percent of the project cost.

There is no deadline to complete projects that start construction this year.

The IRS departed from the Treasury cash grant rules in one significant respect.

There are two ways to show that a project is under construction in time.

One is by showing that “physical work of a significant nature” commenced at the site or at a factory that is making equipment for the project. Work at the factory counts only if done after the project has placed a binding equipment order with the manufacturer.

The other is by showing that the developer “incurred” at least 5 percent of the total project cost. Costs are not usually “incurred” merely by spending money; the developer must take delivery or title to services or equipment.

Many developers gravitated toward the 5 percent test under the Treasury grant program because anyone relying on the physical work test had to show a continuous pattern of construction after work started. There was no similar requirement for the 5 percent test. This let tax equity investors and lenders determine with more certainty at the outset whether a project was under construction in time.

The IRS said it will require developers relying on the 5 percent test to show “continuous efforts” in the future on a project. Developers relying on the physical work test will have to show “continuous construction.”

The IRS guidance is in Notice 2013-29.

The IRS said that it will treat each wind farm as a single project so that work on any part of the project will qualify as the start of construction of the entire project. This is good news for wind developers and was probably the largest open issue for that industry. The IRS has treated each turbine, pad and tower at a wind farm in the past as a separate power plant for production tax credit purposes.

Some renewable energy developers had urged the IRS to adopt a special rule under which anyone completing a project by a deadline would be considered automatically to have started construction in time. The IRS had signaled from the start that it did not feel it had the legal authority to adopt such a provision.

Developers of projects with long construction periods of two years or more had asked for a special rule under which their projects would be treated as under construction if they had obtained all the permits and entered into contracts to start construction, closed on the construction financing or paid at least a fixed dollar amount of costs. The IRS did not make any special provision for such projects.

The IRS addressed several issues that came up during the Treasury cash grant program.

A developer is considered to have started physical work of a significant nature if work is done at a factory on equipment for the project. However, the equipment must be custom made. The IRS said parts that are normally held in inventory will not count.

The IRS confirmed that a developer buying equipment under a master frame agreement can assign its contract rights to the equipment later to a special-purpose project subsidiary and still have the project qualify for tax credits.

The IRS changed the 5 percent test to “at least” 5 percent of the project cost. It was “more than” 5 percent under the Treasury cash grant program.

This article was originally published on Chadbourne & Parke and was republished with permission.

Lead image: Under construction sign via Shutterstock

 

Want more?  Renewable Energy World is hosting a 1-hour webcast on May 1 with author John Marciano as well as Akin Gump's David Burton to discuss how this new definition of "under construction" will impact developers.  Register to attend at this link. 

RELATED ARTICLES

Renewable Energy Finance

Clean Energy ETFs Are on a Tear

Eric Balchunas, Bloomberg Green investing used to be synonymous with losing money. But while the S&P 500 Index is up 2 percent this year, and the MSCI All-Country World Index is up 5 percent, clean energy ETFs have double-digit re...

Wheels, Towers and Trees: Unconventional Renewable Energy Technologies in the Pipeline

Andrew Williams, International Correspondent A number of companies around the world are developing novel technologies in an effort to grab a slice of the global renewable energy market.  Although many of these technologies are simple incremental improvements to e...
UK Parliament Clean Energy Leaders

UK Government Names Clean Energy Cabinet Members

David Appleyard, Contributing Editor With the UK general election now over and a majority Conservative Party government in place, the re-elected Prime Minister David Cameron has now named key members of the government charged with steering the UK’s clean energ...
Microgrids

Coast to Coast and Across the Electric System, Microgrids Provide Benefits to All

Dick Munson, Environmental Defense Fund At the most obvious level, microgrids could disrupt today’s utilities and their regulated-monopoly business model, because they challenge the centralized paradigm. In a nutshell, microgrids are localized power grids that ha...

CURRENT MAGAZINE ISSUE

03/01/2015
Volume 18, Issue 3
file

STAY CONNECTED

To register for our free
e-Newsletters, subscribe today:

SOCIAL ACTIVITY

Tweet the Editors! @megcichon @jennrunyon

FEATURED PARTNERS



EVENTS

Doing Business in Brazil – in partnership with GWEC, the Global Win...

Brazil is one of the most promising markets for wind energy.  Ranke...

Energy Storage USA 2015

Energy Storage USA is the leading conference in the United States focuse...

Wind Power Central America

Wind power projects are expected to reach 46GW of total installed capaci...

COMPANY BLOGS

SunEdison Expands Residential Market Offerings with New PPA, Sales ...

SunEdison has largely focussed on the commercial and utility-scale solar...

Are You Ready for a Natural Disaster?

Guest post by Jenna Clarke  Living in the Shenandoah Valley of Virg...

Deadline for Inclusion in Solar Power World's Top Solar Contractors...

UPDATE: The official deadline for the Solar Power World T...

NEWSLETTERS

Renewable Energy: Subscribe Now

Solar Energy: Subscribe Now

Wind Energy: Subscribe Now

Geothermal Energy: Subscribe Now

Bioenergy: Subscribe Now  

 

FEATURED PARTNERS