The World's #1 Renewable Energy Network for News, Information, and Companies.

IRS Defines Start of Construction for the Production Tax Credit

The Internal Revenue Service explained today what developers must do this year to be considered to have started construction of new renewable energy projects.

The IRS adopted roughly the same definition for start of construction as under the Treasury cash grant program. 

Wind, geothermal, biomass, landfill gas, incremental hydroelectric and ocean energy projects that are under construction by December 2013 will qualify for 10 years of production tax credits on the electricity output or an investment tax credit upon project completion for 30 percent of the project cost.

There is no deadline to complete projects that start construction this year.

The IRS departed from the Treasury cash grant rules in one significant respect.

There are two ways to show that a project is under construction in time.

One is by showing that “physical work of a significant nature” commenced at the site or at a factory that is making equipment for the project. Work at the factory counts only if done after the project has placed a binding equipment order with the manufacturer.

The other is by showing that the developer “incurred” at least 5 percent of the total project cost. Costs are not usually “incurred” merely by spending money; the developer must take delivery or title to services or equipment.

Many developers gravitated toward the 5 percent test under the Treasury grant program because anyone relying on the physical work test had to show a continuous pattern of construction after work started. There was no similar requirement for the 5 percent test. This let tax equity investors and lenders determine with more certainty at the outset whether a project was under construction in time.

The IRS said it will require developers relying on the 5 percent test to show “continuous efforts” in the future on a project. Developers relying on the physical work test will have to show “continuous construction.”

The IRS guidance is in Notice 2013-29.

The IRS said that it will treat each wind farm as a single project so that work on any part of the project will qualify as the start of construction of the entire project. This is good news for wind developers and was probably the largest open issue for that industry. The IRS has treated each turbine, pad and tower at a wind farm in the past as a separate power plant for production tax credit purposes.

Some renewable energy developers had urged the IRS to adopt a special rule under which anyone completing a project by a deadline would be considered automatically to have started construction in time. The IRS had signaled from the start that it did not feel it had the legal authority to adopt such a provision.

Developers of projects with long construction periods of two years or more had asked for a special rule under which their projects would be treated as under construction if they had obtained all the permits and entered into contracts to start construction, closed on the construction financing or paid at least a fixed dollar amount of costs. The IRS did not make any special provision for such projects.

The IRS addressed several issues that came up during the Treasury cash grant program.

A developer is considered to have started physical work of a significant nature if work is done at a factory on equipment for the project. However, the equipment must be custom made. The IRS said parts that are normally held in inventory will not count.

The IRS confirmed that a developer buying equipment under a master frame agreement can assign its contract rights to the equipment later to a special-purpose project subsidiary and still have the project qualify for tax credits.

The IRS changed the 5 percent test to “at least” 5 percent of the project cost. It was “more than” 5 percent under the Treasury cash grant program.

This article was originally published on Chadbourne & Parke and was republished with permission.

Lead image: Under construction sign via Shutterstock

 

Want more?  Renewable Energy World is hosting a 1-hour webcast on May 1 with author John Marciano as well as Akin Gump's David Burton to discuss how this new definition of "under construction" will impact developers.  Register to attend at this link. 

RELATED ARTICLES

Pope Francis

A 9-Minute Guide To Pope Francis’ Encyclical on Climate Change

Jim Lane, Biofuels Digest Pope Francis issued Laudato si’ (Praise Be to You) On the care for our common home, his second encyclical, concerning Catholic doctrine with respect to climate change, consumerism, and development.
US Capitol

Republicans and Democrats Back Bill to Level the Playing Field for Renewable Energy

Vince Font, Contributing Editor U.S. Senators Chris Coons and Jerry Moran are leading a bipartisan effort to reintroduce tax code legislation aimed at leveling the playing field for renewable energy investment. The Master Limited Partnerships Parity Act w...
African vultures wind turbines

Ecological Map Could Save Vultures from Fledgling African Wind Farm Development

Becky Allen, British Ecological Society Ecologists have developed a new map that could help Lesotho's first wind farms generate low carbon energy without putting the region's vulnerable vulture population at risk. The map is part of a study published today in the...
Pope Francis

The Common Goals of the Pope and Clean Energy

Paul Stinson, EDF Pope Francis turned a keen eye toward the environment and the problem of climate change with his encyclical,“Laudato Si” (“Praised Be”). As a clean energy advocate, I’m heartened that Pope Francis recognizes the need t...

CURRENT MAGAZINE ISSUE

Volume 18, Issue 3
1505REW_C11

STAY CONNECTED

To register for our free
e-Newsletters, subscribe today:

SOCIAL ACTIVITY

Tweet the Editors! @megcichon @jennrunyon

FEATURED PARTNERS



EVENTS

Doing Business in South Africa – in partnership with GWEC, the Glob...

Wind Energy in South Africa has been expanding dramatically, growing fro...

CanWEA Winter Solstice Fundraising Dinner

CanWEA Winter Solstice Fundraising Dinner December 1, 2015 Toronto, Ontario

CanWEA Annual Conference and Exhibition

The annual CanWEA Conference & Exhibition has helped companies marke...

COMPANY BLOGS

The Almost There Markets: Just Give ‘Em Some Time

Earlier this year, we reported on recent legalization of third party fin...

Meteorological Technology International Magazine - SENSORS AND SENS...

Over the past 10 years, these sensing technologies have spread tre...

Substrate Feeder for Biogas Facilities

RUD manufactures complete, ready-to-use conveyor systems for transportin...

NEWSLETTERS

Renewable Energy: Subscribe Now

Solar Energy: Subscribe Now

Wind Energy: Subscribe Now

Geothermal Energy: Subscribe Now

Bioenergy: Subscribe Now  

 

FEATURED PARTNERS