The World's #1 Renewable Energy Network for News, Information, and Companies.
Untitled Document

IRS Defines Start of Construction for the Production Tax Credit

The Internal Revenue Service explained today what developers must do this year to be considered to have started construction of new renewable energy projects.

The IRS adopted roughly the same definition for start of construction as under the Treasury cash grant program. 

Wind, geothermal, biomass, landfill gas, incremental hydroelectric and ocean energy projects that are under construction by December 2013 will qualify for 10 years of production tax credits on the electricity output or an investment tax credit upon project completion for 30 percent of the project cost.

There is no deadline to complete projects that start construction this year.

The IRS departed from the Treasury cash grant rules in one significant respect.

There are two ways to show that a project is under construction in time.

One is by showing that “physical work of a significant nature” commenced at the site or at a factory that is making equipment for the project. Work at the factory counts only if done after the project has placed a binding equipment order with the manufacturer.

The other is by showing that the developer “incurred” at least 5 percent of the total project cost. Costs are not usually “incurred” merely by spending money; the developer must take delivery or title to services or equipment.

Many developers gravitated toward the 5 percent test under the Treasury grant program because anyone relying on the physical work test had to show a continuous pattern of construction after work started. There was no similar requirement for the 5 percent test. This let tax equity investors and lenders determine with more certainty at the outset whether a project was under construction in time.

The IRS said it will require developers relying on the 5 percent test to show “continuous efforts” in the future on a project. Developers relying on the physical work test will have to show “continuous construction.”

The IRS guidance is in Notice 2013-29.

The IRS said that it will treat each wind farm as a single project so that work on any part of the project will qualify as the start of construction of the entire project. This is good news for wind developers and was probably the largest open issue for that industry. The IRS has treated each turbine, pad and tower at a wind farm in the past as a separate power plant for production tax credit purposes.

Some renewable energy developers had urged the IRS to adopt a special rule under which anyone completing a project by a deadline would be considered automatically to have started construction in time. The IRS had signaled from the start that it did not feel it had the legal authority to adopt such a provision.

Developers of projects with long construction periods of two years or more had asked for a special rule under which their projects would be treated as under construction if they had obtained all the permits and entered into contracts to start construction, closed on the construction financing or paid at least a fixed dollar amount of costs. The IRS did not make any special provision for such projects.

The IRS addressed several issues that came up during the Treasury cash grant program.

A developer is considered to have started physical work of a significant nature if work is done at a factory on equipment for the project. However, the equipment must be custom made. The IRS said parts that are normally held in inventory will not count.

The IRS confirmed that a developer buying equipment under a master frame agreement can assign its contract rights to the equipment later to a special-purpose project subsidiary and still have the project qualify for tax credits.

The IRS changed the 5 percent test to “at least” 5 percent of the project cost. It was “more than” 5 percent under the Treasury cash grant program.

This article was originally published on Chadbourne & Parke and was republished with permission.

Lead image: Under construction sign via Shutterstock

 

Want more?  Renewable Energy World is hosting a 1-hour webcast on May 1 with author John Marciano as well as Akin Gump's David Burton to discuss how this new definition of "under construction" will impact developers.  Register to attend at this link. 

Untitled Document

RELATED ARTICLES

U.S. Offshore Wind Power Industry Starting to Emerge

Ehren Goossens, Bloomberg A few miles off the coast of Block Island, a new U.S. industry is emerging from the Atlantic Ocean. That’s where Deepwater Wind LLC is installing a massive steel frame, more than 1,500 tons, that sits on the seabed and juts...

100-MW Kenyan Wind Farm Will Help Power Africa

Renewable Energy World Editors As part of President Obama’s Power Africa initiative, the Overseas Private Investment Corporation (OPIC), the U.S. Government’s development finance institution, announced that it committed $233 million in debt financing to ...

Regional News from the July/August 2015 Digital Edition of Renewable Energy World

Renewable Energy World Editors EcoFasten Solar announced that it launched a new mounting "Rock-It System" that it would be displaying during Intersolar. Product compliance was determined through testing per UL Subject 2703, which reviews integr...

With 1.6 GW of Wind Capacity Installed in Q2, American Wind Power Continues To Ramp Up in 2015

David Ward, American Wind Energy Association With 1,661 megawatts (MW) of newly installed wind turbines coming online during the second quarter of 2015 and more than 13,600 MW under construction, American wind power continues to increase its contribution to the U.S. e...

CURRENT MAGAZINE ISSUE

Volume 18, Issue 4
1507REW_C11

STAY CONNECTED

To register for our free
e-Newsletters, subscribe today:

SOCIAL ACTIVITY

Tweet the Editors! @megcichon @jennrunyon

FEATURED PARTNERS



EVENTS

Doing Business in South Africa – in partnership with GWEC, the Glob...

Wind Energy in South Africa has been expanding dramatically, growing fro...

5th Annual Hydro Plant Maintenance

Join maintenance professionals to discuss the challenges in maintenance ...

StartUp Green

AREI, American Renewable Energy Institute, in partnership with ...

COMPANY BLOGS

Clean Energy Patents Maintain High Levels in First Quarter, Solar L...

U.S. patents for Clean Energy technologies from the first quarter of 201...

Koch Professor drops his Koch title, still makes same errors plus s...

The Koch Professor’s title isn’t the only thing that’s...

Fact Check: AWEA represents American wind power

The American Wind Energy Association (AWEA) is proud of its members for ...

NEWSLETTERS

Renewable Energy: Subscribe Now

Solar Energy: Subscribe Now

Wind Energy: Subscribe Now

Geothermal Energy: Subscribe Now

Bioenergy: Subscribe Now  

 

FEATURED PARTNERS