Helpful Guidance for Renewable PTC "Begin Construction" and "Continuous Efforts"

As noted in our prior article, New Twist to the Renewable PTC Extension: Defining "Under Construction," published March 12, 2013, the American Taxpayer Relief Act of 2012 ("ATRA") extends the Production Tax Credit ("PTC") and Investment Tax Credit ("ITC") for certain renewable facilities if construction of the facility begins prior to January 1, 2014, but did not define the "begin construction" requirement.

Find our previous article here.

On April 15, 2013, the IRS provided guidance on this requirement; as expected, it is patterned after the previously issued Section 1603 guidance, with some additional and significant clarifications.  Consistent with prior guidance, the “begin construction” requirement is met if by January 1, 2014:  (i) physical work of a significant nature has commenced; or (ii) more than five percent (5%) of the total project cost of the facility are incurred prior to January 1, 2014.  However, the IRS guidance clarifies that, thereafter, a “continuous program of construction” or “continuous efforts” must also be maintained in the manner described below.  

Physical Work

The “begin construction” requirement is satisfied if “physical work of a significant nature” on tangible personal property integral to the facility has commenced prior to January 1, 2014.  This work may include on-site physical work, or off-site physical work under a binding written contract with another party, such as an equipment supplier.  Once commenced, there must be a continuous program of construction that involves physical work of a significant nature, subject to specific permissible construction disruptions identified by the IRS. 

The term facility includes all components of property that are functionally dependent.  For a wind farm, the electricity-generating wind turbine, the tower, and its supporting pad comprise a single facility.  Under the new guidance, multiple facilities that meet certain specified criteria will be treated as a single facility for purposes of determining when construction has begun.

Tangible personal property “integral to the facility” includes property used to produce electricity, but does not include property used for electrical transmission.  For example, physical work on a transmission tower would not qualify, but physical work on a custom-designed transformer that steps up the voltage of electricity produced at the facility to the voltage needed for transmission would qualify.  Roads used to move materials or equipment to operate and maintain the facility would qualify, but access roads or roads used for employees or visitors would not qualify.  Buildings are not considered an integral part of a facility, unless: 1) the structure is essentially an item of machinery or equipment, or 2) the structure houses property integral to the facility and the use of the structure is so closely related to the use of the housed property that the structure would be expected to be replaced when the property it houses is replaced.

“Physical work of a significant nature” continues to include excavation of foundations, setting anchor bolts, or the pouring of foundations.  Similarly, physical assembly of major components off site at a factory will satisfy this requirement, so long as the developer has a binding contract in place for such work and the components are not held in the manufacturer’s inventory. 

“Physical work of a significant nature” does not include preliminary activities even if the costs of those activities are properly included in the depreciable basis of the facility.  Preliminary activities include planning or designing, securing financing, exploring, researching, clearing a site, obtaining permits, test drilling a geothermal deposit, test drilling to determine soil condition, or excavation to change the contour of the land, or the construction of access roads that are not an integral part of the operation of the facility. 

To be “binding,” a contract must: (i) be entered into prior to work taking place; (ii) be enforceable under local law against the taxpayer or a predecessor; and (iii) not contain a liquidated damages provision.  Work performed under a master contract and then assigned to a new affiliated special purpose vehicle under a new binding written contract may be considered in determining when physical work of a significant nature has begun with respect to a facility.

5 Percent Cost Safe Harbor and “Continuous Efforts”

Alternatively to physical work, construction of a facility will be considered to have commenced if five percent (5%) or more of the total project cost is paid or incurred prior to the January 1, 2014, and, thereafter, “continuous efforts” are made to advance towards completion of the facility.  The total cost of the facility does not include the cost of land or any property that is not integral to the facility. 

The “continuous efforts” requirement is new and does not require physical construction.  Determination of “continuous efforts” is fact-specific, and includes, but is not limited to, the following:  (i) paying or incurring additional amounts included in the total cost of the facility; (ii) entering into binding written contracts for components or future work on construction of the facility; (iii) obtaining necessary permits; and (iv) performing physical work of a significant nature. 

The “continuous efforts” requirement is also subject to the same permitted disruptions and delays as the “continuous program of construction” requirement.

If the facility incurs cost overruns that cause the amounts paid or incurred by the end of 2013 to be less than 5% of the total, the IRS states that the Safe Harbor will not be satisfied, but the PTC/ITC may be claimed with respect to some, but not all, of the individual facilities comprising a single project, so long as the total aggregate cost of those individual facilities is not more than twenty times greater than the amount paid or incurred before January 1, 2014.

This new guidance by the IRS provides much needed clarification for PTC qualification.  With the flexibility provided under the Safe Harbor, diligent developers should be able to plan and commence implementation of projects prior to January 1, 2014, even if actual physical construction of the project starts after that date.

Becky DeCook provides experienced and detailed counsel on telecommunications and energy matters. For more than 20 years she has represented clients in arbitrations, mediations, state and federal court proceedings, and proceedings before state utility commissions throughout the Central and Rocky Mountain regions of the United States, as well as before the Federal Energy Commission and the Federal Communications Commission.

Lead image: Helping hand via Shutterstock

Untitled Document

RELATED ARTICLES

States Already Seek To Delay Clean Power Plan

Andrew Harris, Bloomberg Fifteen states led by coal-rich West Virginia asked a federal court to stall Obama administration rules intended to c...

Stolen Solar Panels and Sabotage A Challenge for Powering India With Renewable Energy

Anindya Upadhyay, Bloomberg Disappointment spread across Tarun Singh’s face when he saw that parts of his solar power microgrid in eastern India’...

Global Renewable Energy Roundup: China, Kenya, Turkey, India Seeking More Renewables

Bloomberg News Editors China is being encouraged by three industry groups to double the nation’s solar-power goal for 2020 to make up for sh...

With Vast Amounts of Geothermal, Wind and Hydropower, Why No Solar In New Zealand?

James Ellsmoor, Contributor New Zealand has built an international brand on environmentalism and the great outdoors. So it is unsurprising that t...

PRESS RELEASES

Appalachian's Energy Center assists counties with landfill gas to energy projects

The Appalachian Energy Center at Appalachian State University recently completed a proj...

Array Technologies’ DuraTrack HZ v3 Continues to (R)evolutionize at SPI

Array Technologies, Inc. (ATI) prepares to showcase its recently launched tracking syst...

Redesigned HydroWorld.com Video Gallery

Hydropower news and information, and interesting promotional announcements are now avai...

30 days to GRC Annual Meeting & GEA Geothermal Energy Expo

The Geothermal Resources Council (GRC) has announced that it is only 30 days to go to t...

FEATURED BLOGS

Appalachian's Energy Center assists counties with landfill gas to energy projects

Activity supported with Z. Smith Reynolds Foundation funding BOONE—The Appalachian Energy Center at Appalachia...

Discounted Room Rates for Geothermal Event end Friday

Discounted room rates for GRC Annual Meeting & GEA Geothermal Energy Expo end Friday Room rates for this prestigi...

3 Reasons To Follow-Up

It’s very important to begin nurturing your relationship with a customer immediately after the project you sold...

Who are the Solar Early Adopters? - the “Tipping Point” is Looming

We all know why people go solar: investment purposes, immediate savings, environmental concerns, and grid independenc...

FINANCIAL NEWS

As an attorney in Moye White LLP's Transaction section, John counsels energy companies in corporate, finance, securities, and development matters. John advises clients on corporate formation and governance, planning and documentation of venture...

CURRENT MAGAZINE ISSUE

Volume 18, Issue 4
1507REW_C11

STAY CONNECTED

To register for our free
e-Newsletters, subscribe today:

SOCIAL ACTIVITY

Tweet the Editors! @jennrunyon

FEATURED PARTNERS



EVENTS

Doing Business in South Africa – in partnership with GWEC, the Glob...

Wind Energy in South Africa has been expanding dramatically, growing fro...

Wind Operator Congress Europe

The UK’s only business-focused O&M event for the European wind...

Distributed Wind Energy Workshop

Description: Distributed wind energy is electricity that is produced for...

COMPANY BLOGS

New coating extends cylinder life 8 times longer than traditional c...

Hydroelectric turbine systems operate in extremely harsh conditions. The...

Clean Energy Patents Maintain High Levels in First Quarter, Solar L...

U.S. patents for Clean Energy technologies from the first quarter of 201...

Koch Professor drops his Koch title, still makes same errors plus s...

The Koch Professor’s title isn’t the only thing that’s...

NEWSLETTERS

Renewable Energy: Subscribe Now

Solar Energy: Subscribe Now

Wind Energy: Subscribe Now

Geothermal Energy: Subscribe Now

Bioenergy: Subscribe Now  

 

FEATURED PARTNERS