US Senators Urge Wind PTC Clarification, But Is It Time To Look Beyond?

A bipartisan group of US Senators, led by Michael Bennet (D-CO) and Jerry Moran (R-KS), have sent an open letter to the US Treasury and IRS asking them to speed up their clarification of new language in the renewable energy production tax credit (PTC).

Other US Senators signing the letter include: Mark Udall (D-CO), Christopher Coons (D-DE), Jeff Merkley (D-OR), Ron Wyden (D-OR), Heidi Heitkamp (D-ND), Sherrod Brown (D-OH), Maria Cantwell (D-WA), Tim Johnson (D-SD), Jeanne Shaheen (D-NH), Angus King (I-ME), Amy Klobuchar (D-MN), Sheldon Whitehouse (D-RI), Al Franken (D-MN), Jack Reed (D-RI), and Barbara Boxer (D-CA). Note that many of these states rank high in installed U.S. wind capacity, and/or biggest growth in wind installations.

The language, added with the 11th hour (probably closer to 11:59th) extension of the wind PTC, changes the criteria for qualification under the PTC as being a form of "under construction." What exactly that means, and thus what companies need to achieve and prove to qualify, is the question — and the main concern as we move weeks ahead into 2013. Some speculate that clarifications could take a cue, or wholesale definition, from what was in the former Section 1603 grant: a certain amount of physical work being put in, and/or a set small percentage of project cost invested.

Many wind industry watchers expect the domestic U.S. wind market will be quiet in 2013. Matt Daprato, North American wind analyst with IHS, projects 2 GW and maybe as much as 3 GW. That follows the blowout 12 GW installed in 2012, much of that rushed to get completed ahead of the previously expiring wind PTC. That frenzy of activity also effectively drained everyone's construction-ready wind project pipelines, as AWEA's latest data shows:

 

Wind power capacity under construction, 4Q12. (Source: American Wind Energy Association)

What spurred this renewed call now for wind PTC clarification? "If this lasts too much longer, there are concerns that it will slow down orders, and cause a problem for everybody," explained Adam Bozzi, spokesperson for Sen. Bennet. His state of Colorado has 6,000 statewide jobs related to the wind industry — including a Vestas factory which may already be in peril, according to recent reports.

One of the few wind developers who is (publicly) expecting a good 2013 is First Wind, though the bulk of its possible 50 percent expansion this year (locations include Maine, Oregon, Washington, Idaho, Utah, and Hawaii) probably will be largely backend-loaded. "We're confident that the Treasury Department understands the need to quickly clarify the language, and we expect them to have details in the near future so that we can plan accordingly," said John Lamontagne, First Wind's director of corporate communications. "We'll be ready to move ahead with our plans when that happens."

First Wind, NextEra, and Detroit Edison all have some projects in their 2013 pipeline, Daprato says, but generally speaking "there is not this hidden pipeline of projects that people aren't talking about." Unless wind projects are already at a very advanced stage, the pending clarification about construction-readiness language in the wind PTC may not matter, at least for this year, he notes. There's a leadtime for getting turbines to the site, or building access roads or infrastructure work, not to mention tying off local permits or any required transmission/substation upgrades. For a sizeable wind project that means "a very, very tight turnaround" to get things moving by year's end. Each passing day moves the needle further ahead. "Most of what's under discussion now for the pipeline is really targeting 2014," he said. If developers are signing contracts at this point, "it's likely for 2014." Assuming a year (or more) is required from shovels-in-the-ground to connection, if clarity about this year's wind PTC doesn't come for weeks or months, we're probably talking about projects that (if they qualify) won't come online until 2015.

Which begs the question: the more we urge and await clarification on the 2013 wind PTC extension, aren't we just biding time until we have to start planning the next last-minute wind PTC renewal for 2014, where the stakes are higher? Developers "are already looking at what they can do next," and will need to quickly refocus on what are the next crop of market opportunities and projects, said Daprato. Ideally those discussions happen "ASAP," providing a longer runway to the outlook and more clarity, he said. History, however, suggests the opposite: another last-minute renewal of the PTC "no sooner than it has to be," and probably a one-year extension clung to a broader bill.

Untitled Document

RELATED ARTICLES

100-MW Kenyan Wind Farm Will Help Power Africa

Renewable Energy World Editors As part of President Obama’s Power Africa initiative, the Overseas Private Investment Corporation (OPIC), the U.S. Government’s development finance institution, announced that it committed $233 million in debt financing to ...

Regional News from the July/August 2015 Digital Edition of Renewable Energy World

Renewable Energy World Editors EcoFasten Solar announced that it launched a new mounting "Rock-It System" that it would be displaying during Intersolar. Product compliance was determined through testing per UL Subject 2703, which reviews integr...

With 1.6 GW of Wind Capacity Installed in Q2, American Wind Power Continues To Ramp Up in 2015

David Ward, American Wind Energy Association With 1,661 megawatts (MW) of newly installed wind turbines coming online during the second quarter of 2015 and more than 13,600 MW under construction, American wind power continues to increase its contribution to the U.S. e...

Some Hope for US Renewable Energy Tax Credits As Extension Bill Passes Committee

Vince Font In a lopsided 23-3 vote, the U.S. Senate Finance Committee voted yesterday to extend a number of renewable energy production tax credits through the end of 2016. The vote allows developers of wind, geothermal, biomass, land...
Jim is Contributing Editor for RenewableEnergyWorld.com, covering the solar and wind beats. He previously was associate editor for Solid State Technology and Photovoltaics World, and has covered semiconductor manufacturing and related industries, ...

CURRENT MAGAZINE ISSUE

Volume 18, Issue 4
1507REW_C11

STAY CONNECTED

To register for our free
e-Newsletters, subscribe today:

SOCIAL ACTIVITY

Tweet the Editors! @megcichon @jennrunyon

FEATURED PARTNERS



EVENTS

Doing Business in South Africa – in partnership with GWEC, the Glob...

Wind Energy in South Africa has been expanding dramatically, growing fro...

StartUp Green

AREI, American Renewable Energy Institute, in partnership with ...

AWEA Offshore WINDPOWER 2015 Conference & Exhibition

Building Up and Trending Forward With the construction of the Block Isla...

COMPANY BLOGS

Clean Energy Patents Maintain High Levels in First Quarter, Solar L...

U.S. patents for Clean Energy technologies from the first quarter of 201...

Koch Professor drops his Koch title, still makes same errors plus s...

The Koch Professor’s title isn’t the only thing that’s...

Fact Check: AWEA represents American wind power

The American Wind Energy Association (AWEA) is proud of its members for ...

NEWSLETTERS

Renewable Energy: Subscribe Now

Solar Energy: Subscribe Now

Wind Energy: Subscribe Now

Geothermal Energy: Subscribe Now

Bioenergy: Subscribe Now  

 

FEATURED PARTNERS