Small Wind Profile: Two Wind Turbines Supply Electricity to U.S. Border Station

Following the terrorist attacks of 9/11, the U.S. initiated a program to expand and upgrade its border stations with Canada and Mexico. Federal agencies have aggressive clean energy and carbon reduction goals, and the federal government's General Services Administration (GSA) is responsible for many of the federal government's buildings, including energy procurement. While the U.S. operates 168 border stations, in GSA's New England Region, there are 47 land ports of entry (LPOEs), ranging in size from 2,000 to 100,000 square feet. With more sophisticated electronic equipment being deployed in these stations, the electricity requirements are increasing.

Staff at the GSA Boston office had been evaluating the wind energy opportunity since 2001. The combination of the remote Jackman, Maine, LPOE upgrade and the availability of ARRA [American Recovery and Reinvestment Act] funds led Roman Piaskoski, Chief of the Energy, Utilities & Environment Branch, to implement a distributed wind generation pilot project consisting of two Northern Power Systems 100-kW units. The turbines were installed in September 2010 but were not interconnected and on line with Hydro-Quebec (H-Q) until April 2011. With a measured wind speed of 6.1 mps (13.7 mph) at their 37-m (121-ft) hub height, the two units are expected to produce 400,000 kWh per year. The project goal was for the turbines to supply 50 percent of the Jackman LPOE’s annual electricity.

The permitting was relatively straightforward as the site is GSA property and not close to residential areas. It received Federal Aviation Administration and Maine Department of Environmental Protection approvals, with no public resistance.

However, as can happen with first ventures, the project faced challenges, even with proven equipment. H-Q had existing net metering regulations for generators < 60 kW and > 1 MW, and so the 100-kW turbines landed in H-Q’s "blind spot." GSA had initially considered 10-kW units until the Jackman LPOE was dramatically upgraded, and H-Q assumed that GSA proceeded with the original turbine capacity. With the two 100-kW units, H-Q required the installation of a remote shutdown system with a dedicated phone line. Factor in the language differences and less-than-ideal communications, and the result was a six-month delay between installation and operation. In addition, the installer implemented a special ice-melt system, which failed, caused frequent system shutdowns and eventually resulted in the need for a new set of blades. (Northern Power did not endorse the system.)

Since resolving these issues, the Energy, Utilities & Environmental Branch has been pleased with the turbines’ performance and Northern Power’s technical assistance and maintenance. Piaskoski believes that the pilot successfully demonstrates that wind energy can contribute to GSA’s energy and environmental goals through application to LPOEs in windy locations. He recently presented the project at the GovEnergy conference as a successful wind pilot project. While the decreasing GSA budget may not be sufficient to expand the number of LPOEs, an opportunity remains for wind to participate in the upgrading and greening of existing facilities.

This article was originally published in AWEA's Wind Energy Weekly and was republished with permission. It is one in a series of case studies included in AWEA's recently published Small Wind Turbine Market Report Year End 2011.

Lead image: Boston skyline via Shutterstock

Untitled Document

Get All the Renewable Energy World News Delivered to Your Inbox

Subscribe to Renewable Energy World or email newsletter today at no cost and receive the latest news and information.

 Subscribe Now


offshore wind

Hitachi Plans to Add Production Line for Offshore Wind Parts

Chisaki Watanabe, Bloomberg Hitachi Ltd. plans to expand its reach into the market for offshore wind projects by adding a production line to make...
Renewable energy

Leading US ICT Companies Renewables Use at 14%, and Growing

Andrew Burger Electricity consumption in the global information and communications technology (ICT) industry is growing rapidly. An...
Wind farms

Western: Streamlined Environmental Review Process for Wind Farms in Midwest ‘Takes Effect Right Away’

Jennifer Delony Western in an Aug. 26 record of decision (ROD) adopted a standardized process for collecting information and evaluati...

NextEra Commits to Hawaii’s Clean Power Goal, Local Management

Lynn Doan, Bloomberg NextEra Energy Inc. and Hawaiian Electric Industries Inc. made 50 new commitments as part of their proposal to merge ...


$100 Discount on 5-day Advanced PV Project Experience Workhop

Upcoming 5-day Workshops: Nov. 7 - 11 Feb. 6 - 10

IREC Announces Changes in Regulatory Team

The Interstate Renewable Energy Council (IREC), a not-for-profit organization which for...

IREC Awarded New Funding to Advance Digital Credentials

The Interstate Renewable Energy Council (IREC) proudly announces funding for an innovat...

US Solar - Green Planet Festival Highlights Solar Energy and Solar Training This Weekend

US Solar Institute (USSI) is excited to announce that they are the educational sponsor ...


ENER-G CHP technology selected for major London housing scheme

ENER-G has been selected to supply combined heat and power (CHP) technology for phase two of the Leopold Estate housi...

What's On The Card?

Think back to the last networking event you attended. You probably walked out with at least a couple dozen business c...


Necessity is the mother of innovation. Our planet is going through major changes in climate. This of course will affe...

Georgia Legislature Approves PPA’s, Florida Hoping to Follow

Ah, the sunny south, the land of peaches, oranges and solar potential. I’m talking about Georgia and Florida he...


Carl is Editor & Publications Manager at the American Wind Energy Association, where has worked since 2006. At AWEA he oversees AWEA's online and print publications including the Wind Energy Weekly, Windpower Update, and other products. He has wor...


Volume 18, Issue 4


To register for our free
e-Newsletters, subscribe today:


Tweet the Editors! @jennrunyon



Doing Business in Europe – in partnership with GWEC, the Global Win...

There is now 128.8 GW of installed wind energy capacity in the EU (appro...

Doing Business in South Africa – in partnership with GWEC, the Glob...

Wind Energy in South Africa has been expanding dramatically, growing fro...

Distributed Wind Energy Workshop

Description: Distributed wind energy is electricity that is produced for...


Clean Energy Patents Maintain High Levels in First Quarter, Solar L...

U.S. patents for Clean Energy technologies from the first quarter of 201...

Koch Professor drops his Koch title, still makes same errors plus s...

The Koch Professor’s title isn’t the only thing that’s...

Fact Check: AWEA represents American wind power

The American Wind Energy Association (AWEA) is proud of its members for ...


Renewable Energy: Subscribe Now

Solar Energy: Subscribe Now

Wind Energy: Subscribe Now

Geothermal Energy: Subscribe Now

Bioenergy: Subscribe Now