Feds Pick 7 Projects to Speed Up Transmission Line Buildout

Talks about the need to modernize the transmission grid have swirled around in the renewable energy world for a while now, but big challenges in areas such as permitting remain for accomplishing that goal. The federal government says it wants to help, and it announced seven pilot projects on Wednesday to show how it could speed up the regulatory processes.

Nine federal agencies formed the Rapid Response Team for Transmission to oversee the seven pilot projects, which the team chose to show how proposals in various stages of permitting processes will move faster than before. But federal officials on the team declined to quantify just how fast that would be. A transmission project could take anywhere from five to 15 years to secure all the permits, said Lauren Azar, senior advisor to the Energy Secretary Steven Chu, during a conference call on Wednesday. Don’t count on an extraordinary cut to the amount of time it will take given the complexity of transmission projects and the potential need to secure not just federal but state permits.

“We need a better grid and we need that to build a better economy,” Azar said. “Transforming our grid won’t happen overnight. But we do need to take a long term view and begin that transformation today.”

More and better transmission lines are considered necessary for ferrying the growing amount of solar, wind and geothermal electricity in the country. Utilities are investing in these projects not only to serve their own territories but also to export renewable energy to nearby states that have clean power mandates. The U.S. Department of Energy approved a $343 million loan guarantee earlier this year to build a 235-mile, 500-kilovolt line from northern to southern Nevada. NV Energy, one of the project developers, is also working on a larger transmission project to bring wind and solar power from Wyoming, Idaho and Nevada to California, where the utilities are under pressure to get 33 percent of their electricity from renewable sources by 2020.

The effort to expedite transmission projects also has to do with creating jobs. Job creation is a thorny challenge for the Obama administration and Congress and is already taking center stage in election politics.

“This is not just about jobs specifically connected to transmission lines. It also sends a strong message to the entire industry and give them the confidence to increase generation capacities,” said Agriculture Secretary Tom Vilsack.

Plans to work together to upgrade and build more transmission lines began two years ago, when the nine federal agencies signed a memorandum of understanding to officially kickstart the initiative. After meeting with utilities and others in the power industry, the response team picked the seven projects. The agencies involved include the departments of energy, interior, agriculture, commerce and defense, as well as the Environmental Protection Agency and the Federal Regulatory Commission.

The federal response team will work on three main areas: coordinate regulatory reviewing and permitting steps between federal and state agencies, take a “uniform and consistent approach” in working with American Indian tribal governments, and resolve disputes among agencies quickly. You can track the progress of the seven pilot projects by clicking here.

The agriculture department, for one, already has made administrative changes to open up the national forests for transmission development, Vilsack said.

If all goes well, transmission lines will be built across 12 states: Arizona, Colorado, Idaho, Minnesota, New Mexico, Nevada, Wyoming, Utah, New Jersey, Pennsylvania, Oregon, and Wisconsin. The first project to start construction will likely take place in the fall of 2012, said Interior Secretary Ken Salazar.

Among the seven pilot projects, the Susquehanna-to-Roseland line is among the farthest along the permitting process, Azar said. The project, proposed by PPL and Public Service Electric and Gas Co., will build 145 miles of 500-kilovolt line from Pennsylvania to New Jersey and several substations. The project could be built and begin operation in the spring of 2015.

Untitled Document

Get All the Renewable Energy World News Delivered to Your Inbox - FREE!

Subscribe to Renewable Energy World Magazine and our award-winning e-Newsletter to stay up to date on current news and industry trends.

 Subscribe Now



Evaluating the Case for Module-Level Shutdown

Hannes Knopf With 2014 NEC adoption in full swing, many are anticipating what the next version of the code will hold for the PV in...

A Case Study in Energy-Transition Momentum

Tim King South Australia is clearly at the forefront of the global energy transition as it establishes a fast-moving model oth...

Listen Up: Can I Get Solar if my Roof is Shaded?

The Energy Show on Renewable Energy World Rooftop solar panels only work when they are in direct sunlight. So if you have a partially shaded roof, the output o...

US Senate Democrats Unveil Energy Bill That Restores PTC and Extends ITC

Brian Eckhouse, Bloomberg Senate Democrats unveiled a bill that would provide more tax credits for renewable energy while killing some tax ince...


Array Technologies Finalizes Shipments to E.ON’s Maricopa West Solar Project

Array Technologies, Inc. (ATI) has completed DuraTrack® HZ shipments to the 20 MW (ac) ...

B.C. Energy Minister to provide keynote at renewables for mines summit.

BC Minister of Energy and Mines to address the challenges of providing alternative powe...

Mining leaders seek renewables solutions at Toronto Summit

The global mining sector is facing a tough business environment with low commodity pric...

American Renewable Energy Institute Gears Up for 12th Annual Summit

"Racing Climate Change: Green Bridge with China, The Road to Paris” is the theme of th...


New Mexico Attracts Jobs and Revenues with Renewable Energy Tax Credit

New Mexico has abundant fossil fuel resources: in 2013, it ranked sixth in the nation for crude oil production, seven...

The Vice President Stole My Show (Not Really)

When I finished my Solar Power International (SPI) panel discussing what future opportunities the panelists saw in so...

The Value Of The Building

If you’re selling efficiency solutions in the built environment, you may find yourself being asked by your pros...

Sewage provides energy through processing

Many nations are investing in new technology to turn sewage waste into usable energy. Japan has recently revised its ...


Ucilia Wang is a California-based freelance journalist who writes about renewable energy. She previously was the associate editor at Greentech Media and a staff writer covering the semiconductor industry at Red Herring. In addition to Renewable En...


Volume 18, Issue 4


To register for our free
e-Newsletters, subscribe today:


Tweet the Editors! @jennrunyon



Successfully Integrating Solar: A Proactive Approach

•      What does the increasing solar penetrati...

Solar Power Northeast

  From the team that produced Solar Power Southeast and the sol...

Solar Power Asset Management and Performance

SEIA and SEPA collaborated with industry leaders to present the first ev...


Fast facts: 4 things you need to know about the state of solar fina...

Fast facts: 4 things you need to know about the state of solar financing...

10 Questions You Should Be Asking

Tony Robbins is fond of saying that the quality of your life is directly...

Join us at the New Solar Power Northeast

From the team that produced Solar Power Southeast and the sold out P...


Renewable Energy: Subscribe Now

Solar Energy: Subscribe Now

Wind Energy: Subscribe Now

Geothermal Energy: Subscribe Now

Bioenergy: Subscribe Now