China Seeks Big Wind in a Push To Standardize Project Size

The Chinese government is now working on new procedures that will standardize the inspection and approval process for wind power projects in a move to address the wind power grid connection and operation security issues that dog the sector's development.

What has been termed as non-mainstream small wind power projects, specifically those with installed capacity of 49.5 MW, have become the focus of severe criticism. Companies had been favoring projects below 50 MW as those above this capacity required state-level approval, while projects below 50 MW could go live following approval at the local level.

To avoid the complicated state-level approval procedure and take advantage of the much more expedient local level process, as well as the lower level of investment and easier connection to the grid, many companies opted for 49.5 and 49.9MW projects, creating a massive gray area just below the radar of the state-level approval system.

As a result, this mass of small projects not under the review of state-level authorities has created a huge misalignment between the country’s wind power plans and power network plans.

A report from Hydrochina Corporation (formerly the Administration of Water Resources and Hydropower Planning and Design), revealed that during 2009, 187 wind farm projects were approved, and 111 of those projects were at 49.5-MW capacity, accounting for 59 percent of the year’s total approvals.

As for the huge imbalance created by local-level approvals, State Grid Corporation of China (SGCC) executive vice president Shu Yinbiao recently leveled this criticism. “We are completely in the dark about the locally approved wind farms below 50 MW, and as a result, we cannot implement the corresponding supporting infrastructure, leading to a major gap between wind power development and power network construction,” Yinbiao said.

The SGCC’s and provincial-level inspection and approval procedures are essentially the same. However, as the SGCC deals with projects spread across the country, the regulatory authority has fully standardized the process. By contrast, provincial authorities handle fewer projects, are highly flexible and time to approval is short.

Documents leaked to date show that 50-MW projects will continue to be approved at the state level while those under may still be approved at the local level as long as their approvals are filed with the National Development and Reform Commission. However, going forward, local governments approving the smaller projects will now need sign off from the National Energy Administration in order to proceed.

“The procedures will begin with four focus points, including governmental administration, wind farm operation, wind power equipment performance and power grid dispatching,” said Deputy director-general Shi Lishan of the New and Renewable Energy Department of China’s National Energy Administration. The new approval process under development shows the government’s willingness to use administrative methods to control its wind power sector. The goal is to align and optimize the development plans of the country’s wind power industry with those of its energy grid.

In response to this, wind power developers are quietly upgrading their strategies, and said they will adapt to the changing conditions and shift their development model for wind power projects. A general manger at one of China’s leading wind power companies said that they will gradually reduce the number of projects below 50 MW capacity. “We will also invest in establishing wind farms with capacity of above 100 MW, in conformity with the national government’s planned large wind power bases,” he said.

As the country continues to tighten the project approval process and the development efficiency between the small and large projects become the same, these companies will start to incorporate the small wind power projects into larger ones, and work at the state-level to facilitate integration into the country’s larger projects.

Untitled Document

RELATED ARTICLES

Sinovel Wind’s Loss Widens on Fewer Orders, Asset Impairment

Reed Landberg, Iain Wilson, Abhay Singh, Bloomberg Sinovel Wind Group Co., once China’s biggest supplier of wind turbines, said its loss more than doubled in the first ...

Wind Power is Breaking Down International Border Barriers

Vince Font In an important “model of collaboration” between the U.S. and Mexico, the first ever cross-border wind farm has been ...

Why Do Germany’s Electricity Prices Keep Falling?

Rachel Morison, Bloomberg Chancellor Angela Merkel cemented Germany’s shift toward an economy powered by renewable energy in 2010 with her “Ene...

German Renewables Investors To Fund Iranian Wind Farm

Anna Hirtenstein, Bloomberg Development Environment Arvand Co., a German-Iranian renewables developer, signed an agreement to build a 48-megawatt...

PRESS RELEASES

Array Technologies’ DuraTrack HZ v3 Continues to (R)evolutionize at SPI

Array Technologies, Inc. (ATI) prepares to showcase its recently launched tracking syst...

Appalachian's Energy Center assists counties with landfill gas to energy projects

The Appalachian Energy Center at Appalachian State University recently completed a proj...

Redesigned HydroWorld.com Video Gallery

Hydropower news and information, and interesting promotional announcements are now avai...

30 days to GRC Annual Meeting & GEA Geothermal Energy Expo

The Geothermal Resources Council (GRC) has announced that it is only 30 days to go to t...

FEATURED BLOGS

Transitioning to Net-Zero Living

Judith and Jeffrey adore living in Belfast, Maine – a quaint harbor town of Belfast, Maine. They previously res...

The True Cost of Electric Vehicles in Australia

In order to avoid increased congestion, further greenhouse warming and lessen Australia’s reliance on imported ...

The Coming Multi-trillion Dollar Energy Investment Drive

In coming years, a multi-trillion dollar low-emission energy investment drive will get underway. Three catalysts wil...

The Perfect Elevator Pitch

The elevator pitch is a concise statement that grabs attention and communicates value, ideally leading to a next step...

FINANCIAL NEWS

Nanjing Shanglong Communications Liu Yuanyuan is Director of Operations and Co-Founder of Nanjing Shanglong Communications. Liu Yuanyuan previously held the position of office manager at the London Financial Times' China translation and editoria...

CURRENT MAGAZINE ISSUE

Volume 18, Issue 4
1507REW_C11

STAY CONNECTED

To register for our free
e-Newsletters, subscribe today:

SOCIAL ACTIVITY

Tweet the Editors! @jennrunyon

FEATURED PARTNERS



EVENTS

Doing Business in Europe – in partnership with GWEC, the Global Win...

There is now 128.8 GW of installed wind energy capacity in the EU (appro...

Doing Business in South Africa – in partnership with GWEC, the Glob...

Wind Energy in South Africa has been expanding dramatically, growing fro...

Distributed Wind Energy Workshop

Description: Distributed wind energy is electricity that is produced for...

COMPANY BLOGS

Clean Energy Patents Maintain High Levels in First Quarter, Solar L...

U.S. patents for Clean Energy technologies from the first quarter of 201...

Koch Professor drops his Koch title, still makes same errors plus s...

The Koch Professor’s title isn’t the only thing that’s...

Fact Check: AWEA represents American wind power

The American Wind Energy Association (AWEA) is proud of its members for ...

NEWSLETTERS

Renewable Energy: Subscribe Now

Solar Energy: Subscribe Now

Wind Energy: Subscribe Now

Geothermal Energy: Subscribe Now

Bioenergy: Subscribe Now  

 

FEATURED PARTNERS